Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
35
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0627 # 12 Y:2024 | 12 | 2024 | INSTALL WIND POWERED ELECTRIC GENERATOR | $364,913 | $422,153 | n/a |
SF0627 # 11 Y:2024 | 11 | 2024 | REDUCE EXCESSIVE BOILER BLOWDOWN | $758 | $3,995 | n/a |
SF0627 # 10 Y:2024 | 10 | 2024 | HEAT WATER WITH EXHAUST HEAT | $23,270 | $67,410 | n/a |
SF0627 # 09 Y:2024 | 09 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,796 | $17,995 | n/a |
SF0627 # 08 Y:2024 | 08 | 2024 | INSULATE FEEDWATER TANK | $31,296 | $45,008 | n/a |
SF0627 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,292 | $0 | n/a |
SF0627 # 02 Y:2024 | 02 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $2,331 | $0 | n/a |
SF0627 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,552 | $140 | n/a |
SF0627 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,465 | $650 | n/a |
SF0627 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $828 | $98 | n/a |
SF0627 # 06 Y:2024 | 06 | 2024 | INSULATE BARE EQUIPMENT | $772 | $338 | n/a |
SF0627 # 07 Y:2024 | 07 | 2024 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $56,762 | $75,338 | n/a |
SJ0027 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,837 | $1,550 | n/a |
SJ0027 # 03 Y:2024 | 03 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,400 | $0 | n/a |
SJ0027 # 02 Y:2024 | 02 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $32,211 | $22,296 | n/a |
SJ0027 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $89,704 | $333,155 | n/a |
SJ0026 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $79,569 | $266,719 | n/a |
SJ0026 # 02 Y:2024 | 02 | 2024 | INSULATE BARE EQUIPMENT | $653 | $607 | n/a |
SJ0026 # 03 Y:2024 | 03 | 2024 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $1,192 | $888 | n/a |
SJ0026 # 04 Y:2024 | 04 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $123,957 | $18,405 | n/a |
SJ0026 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,978 | $9,706 | n/a |
SJ0026 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,177 | $9,200 | n/a |
SJ0026 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $400 | $0 | n/a |
SJ0026 # 08 Y:2024 | 08 | 2024 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $4,132 | $25,650 | n/a |
SJ0026 # 09 Y:2024 | 09 | 2024 | REDUCE EXCESSIVE BOILER BLOWDOWN | $2,261 | $1,017 | n/a |