Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
79
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0045 # 04 Y:2009 | 04 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,645 | $0 | Implemented |
MZ0045 # 05 Y:2009 | 05 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $23,660 | $0 | Implemented |
MZ0045 # 03 Y:2009 | 03 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,734 | $950 | Implemented |
MZ0045 # 02 Y:2009 | 02 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,746 | $4,200 | Not Implemented |
MZ0045 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,876 | $46,050 | Implemented |
MZ0044 # 06 Y:2009 | 06 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,312 | $10,000 | Not Implemented |
MZ0044 # 05 Y:2009 | 05 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,268 | $0 | Not Implemented |
MZ0044 # 04 Y:2009 | 04 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,600 | $850 | Implemented |
MZ0044 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,160 | $5,600 | Implemented |
MZ0044 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,991 | $38,600 | Implemented |
MZ0044 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $802 | $460 | Not Implemented |
MZ0044 # 07 Y:2009 | 07 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,155 | $10,000 | Not Implemented |
MZ0046 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,025 | $14,100 | Implemented |
MZ0046 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $18,406 | $1,380 | Implemented |
MZ0046 # 04 Y:2009 | 04 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $53,749 | $1,300 | Implemented |
MZ0046 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54,631 | $54,630 | Implemented |
MZ0046 # 09 Y:2009 | 09 | 2009 | UPGRADE CONTROLS ON COMPRESSORS | $10,100 | $8,000 | Implemented |
MZ0046 # 07 Y:2009 | 07 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $205,683 | $30,000 | Not Implemented |
MZ0046 # 06 Y:2009 | 06 | 2009 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $8,620 | $1,800 | Implemented |
MZ0046 # 08 Y:2009 | 08 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,483 | $0 | Implemented |
MZ0046 # 05 Y:2009 | 05 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,771 | $0 | Implemented |
MZ0043 # 06 Y:2009 | 06 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,995 | $1 | Implemented |
MZ0043 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $2,319 | $480 | Implemented |
MZ0043 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,595 | $20,400 | Implemented |
MZ0043 # 05 Y:2009 | 05 | 2009 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $7,387 | $3,600 | Implemented |