Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0170 # 01 Y:2003 | 01 | 2003 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $210,423 | $300,000 | Not Implemented |
LE0170 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $425 | $825 | Not Implemented |
LE0170 # 02 Y:2003 | 02 | 2003 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $2,647 | $7,000 | Implemented |
LE0170 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $440 | $560 | Not Implemented |
LE0170 # 04 Y:2003 | 04 | 2003 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $367 | $0 | Implemented |
LE0170 # 03 Y:2003 | 03 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $952 | $0 | Implemented |
LE0156 # 01 Y:2003 | 01 | 2003 | SIZE AIR HANDLING GRILLS/ DUCT/S COILS TO MINIMIZE AIR RESISTANCE | $1,112 | $870 | Implemented |
LE0156 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $1,413 | $0 | Implemented |
LE0156 # 03 Y:2003 | 03 | 2003 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,466 | $0 | Not Implemented |
LE0156 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $844 | $0 | Not Implemented |
LE0156 # 04 Y:2003 | 04 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,340 | $0 | Implemented |
LE0156 # 07 Y:2003 | 07 | 2003 | INSTALL OCCUPANCY SENSORS | $239 | $600 | Implemented |
LE0156 # 02 Y:2003 | 02 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,320 | $750 | Not Implemented |
LE0155 # 01 Y:2003 | 01 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $947 | $0 | Implemented |
LE0155 # 02 Y:2003 | 02 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,269 | $2,500 | Not Implemented |
LE0155 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,520 | $0 | Implemented |
LE0155 # 04 Y:2003 | 04 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,873 | $0 | Not Implemented |
LE0155 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,288 | $300 | Implemented |
LE0155 # 06 Y:2003 | 06 | 2003 | INSULATE BARE EQUIPMENT | $588 | $925 | Not Implemented |
LE0155 # 07 Y:2003 | 07 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $795 | $500 | Not Implemented |
LE0155 # 08 Y:2003 | 08 | 2003 | PAY UTILITY BILLS ON TIME | $4,771 | $0 | Implemented |
LE0155 # 09 Y:2003 | 09 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $273 | $0 | Implemented |
LE0155 # 10 Y:2003 | 10 | 2003 | USE SYNTHETIC LUBRICANT | $251 | $200 | Implemented |
LE0152 # 05 Y:2003 | 05 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,965 | $0 | Not Implemented |
LE0152 # 06 Y:2003 | 06 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,694 | $1,312 | Implemented |