IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

60

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1058 # 03 Y:2021 03 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,252 $7,778 Implemented
OK1058 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $455 $2,130 Not Implemented
OK1058 # 04 Y:2021 04 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $185 $700 Implemented
OK1058 # 01 Y:2021 01 2021 OPTIMIZE PLANT POWER FACTOR $1,800 $3,000 Not Implemented
OK1057 # 04 Y:2021 04 2021 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,960 $0 Implemented
OK1057 # 01 Y:2021 01 2021 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $10,601 $1,701 Implemented
OK1057 # 03 Y:2021 03 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $533 $1,400 Not Implemented
OK1057 # 02 Y:2021 02 2021 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $12,483 $56,000 Implemented
OK1056 # 01 Y:2021 01 2021 RECOVER AND REUSE WASTE MATERIAL $10,400 $0 Not Implemented
OK1056 # 02 Y:2021 02 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,775 $3,987 Not Implemented
OK1056 # 03 Y:2021 03 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $425 $629 Implemented
OK1056 # 04 Y:2021 04 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $46 $162 Implemented
OK1052 # 01 Y:2021 01 2021 OPTIMIZE PLANT POWER FACTOR $1,512 $6,000 Not Implemented
OK1052 # 02 Y:2021 02 2021 USE RADIANT HEATER FOR SPOT HEATING $4,517 $19,500 Not Implemented
OK1052 # 03 Y:2021 03 2021 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,322 $0 Not Implemented
OK1052 # 04 Y:2021 04 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,648 $13,284 Implemented
OK1052 # 05 Y:2021 05 2021 INSTALL OCCUPANCY SENSORS $2,203 $586 Not Implemented
OK1049 # 03 Y:2021 03 2021 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,589 $0 Implemented
OK1049 # 04 Y:2021 04 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,601 $1,060 Implemented
OK1049 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $552 $820 Implemented
OK1049 # 01 Y:2021 01 2021 OPTIMIZE PLANT POWER FACTOR $5,159 $6,000 Not Implemented
OK1047 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,774 $6,045 Implemented
OK1047 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,212 $1,242 Implemented
OK1047 # 01 Y:2021 01 2021 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $9,181 $17,737 Implemented
OK1047 # 04 Y:2021 04 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $876 $500 Implemented