Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
388
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2508 # 01 Y:2025 | 01 | 2025 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $272 | $6,858 | n/a |
UW2508 # 04 Y:2025 | 04 | 2025 | INSTALL DEDICATED MIXING EQUIP TO OPTIMIZE REUSE OF USED RINSEATE & TO PRECLUDE THE NEED FOR INTER-RUN CLEANING | $116,528 | $582,640 | n/a |
UW2508 # 03 Y:2025 | 03 | 2025 | INSTALL OCCUPANCY SENSORS | $841 | $8,448 | n/a |
UW2508 # 02 Y:2025 | 02 | 2025 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $665 | $8,888 | n/a |
UW2506 # 02 Y:2025 | 02 | 2025 | UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS | $14,113 | $1,255 | n/a |
UW2506 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $75,836 | $644,978 | n/a |
UW2506 # 07 Y:2025 | 07 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,155 | $25,000 | n/a |
UW2506 # 05 Y:2025 | 05 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,528 | $15,530 | n/a |
UW2506 # 01 Y:2025 | 01 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $8,164 | $187,200 | n/a |
UW2506 # 04 Y:2025 | 04 | 2025 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,688 | $54,000 | n/a |
UW2506 # 06 Y:2025 | 06 | 2025 | INSTALL OCCUPANCY SENSORS | $6,019 | $7,709 | n/a |
UW2505 # 04 Y:2025 | 04 | 2025 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $55,282 | $123,500 | n/a |
UW2505 # 02 Y:2025 | 02 | 2025 | REPAIR OR REPLACE STEAM TRAPS | $30,117 | $4,550 | n/a |
UW2505 # 05 Y:2025 | 05 | 2025 | INSULATE FEEDWATER TANK | $815 | $443 | n/a |
UW2505 # 03 Y:2025 | 03 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $20,963 | $191,676 | n/a |
UW2505 # 06 Y:2025 | 06 | 2025 | USE OPTIMUM THICKNESS INSULATION | $950 | $3,710 | n/a |
UW2505 # 01 Y:2025 | 01 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,747 | $15,000 | n/a |
UW2504 # 06 Y:2025 | 06 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $32,988 | $55,500 | n/a |
UW2504 # 05 Y:2025 | 05 | 2025 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $9,594 | $149,864 | n/a |
UW2504 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $60,995 | $262,084 | n/a |
UW2504 # 01 Y:2025 | 01 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $24,319 | $2,741 | n/a |
UW2504 # 04 Y:2025 | 04 | 2025 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $16,531 | $210,600 | n/a |
UW2504 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,637 | $15,000 | n/a |
UW2503 # 02 Y:2025 | 02 | 2025 | INSULATE FEEDWATER TANK | $1,063 | $489 | n/a |
UW2503 # 04 Y:2025 | 04 | 2025 | IMPROVE COMBUSTION CONTROL CAPABILITY | $52,839 | $2,112 | n/a |