Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1990 |
Principal Product | COMMERCIAL PRINTING |
NAICS | n/a |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 11,600,000 Pounds |
Production Hrs. Annual | 5,976 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $404,260 | 8,257,034 | kWh | $0.05 |
Natural Gas | $61,005 | 12,672 | MMBtu | $4.81 |
TOTAL ENERGY COSTS | $465,265 | |||
RECOMMENDED SAVINGS* | $8,510 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,500 |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $4,600 Cost: - |
$4,600 | - | - | - |
$4,600 - kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $2,010 Cost: - |
$2,010 | 76,202 | - | - |
$2,010 76,202 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2522 ISOLATE HOT OR COLD EQUIPMENT |
Savings: $1,090 Cost: $500 |
$1,090 | 41,325 | - | - |
$1,090 41,325 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $810 Cost: $550 |
$610 | 15,826 | $200 | - |
$610 15,826 kWh |
$200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,510 Cost: $1,050 |
$8,310 | 133,353 | $200 | - | $8,310 133,353 kWh |
$200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,500 Cost: $1,050 |
$6,300 | 57,151 | $200 | - | $6,300 57,151 kWh |
$200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes |