IAC Assessment: AM0123
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0123
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1991
Principal Product PRINTED NEWSPAPER ADVERTISEMENTS
NAICS n/a
SIC 2752 - Commercial Printing, Lithographic
Sales $10,000,000-$50,000,000
# of Employees 170
Plant Area (Sq.Ft.) 0
Annual Production 21,108,000 Pounds
Production Hrs. Annual 4,896
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $212,190 3,788,980 kWh $0.06
Natural Gas $62,645 12,121 MMBtu $5.17
TOTAL ENERGY COSTS $274,835
RECOMMENDED SAVINGS* $35,697 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$24,600
Cost:
$50,000
- - $24,600 6,000 -
-
kWh
$24,600
6,000
MMBtu
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$8,786
Cost:
$28,548
$8,786 - - - $8,786
-
kWh
-
-
MMBtu
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$769
Cost:
$2,520
$769 - - - $769
-
kWh
-
-
MMBtu
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$490
Cost:
-
$490 7,620 - - $490
7,620
kWh
-
-
MMBtu
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$480
Cost:
$200
$480 - - - $480
-
kWh
-
-
MMBtu
06: 2.6232 INSTALL SET-BACK TIMERS Savings:
$472
Cost:
-
$472 8,206 - - $472
8,206
kWh
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$100
Cost:
$100
$100 1,172 - - $100
1,172
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$35,697
Cost:
$81,368
$11,097 16,998 $24,600 6,000 $11,097
16,998
kWh
$24,600
6,000
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas