Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1997 |
Principal Product | Molded rubber products |
NAICS | n/a |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 38 |
Plant Area (Sq.Ft.) | 26,000 |
Annual Production | 600,000 Pieces |
Production Hrs. Annual | 5,952 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,464 | 1,474,209 | kWh | $0.05 |
Electricity Demand | $18,903 | 3,941 | kW-months/year | $4.80 |
Natural Gas | $20,253 | 5,200 | MMBtu | $3.89 |
TOTAL ENERGY COSTS | $108,620 | |||
RECOMMENDED SAVINGS* | $12,587 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,007 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $2,220 Cost: - |
$(-1,510) | (-32,825) | $5,600 | 1,262 | - | - | - | - | $(-1,870) | - | - | - |
$(-1,510) (-32,825) kWh |
$5,600 1,262 kW-months/year |
- - MMBtu |
- - lb |
$(-1,870) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $4,380 Cost: $10,440 |
- | - | - | - | $4,380 | 1,125 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,380 1,125 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $1,580 Cost: $430 |
- | - | - | - | $1,580 | 406 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,580 406 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7145 INSTALL SKYLIGHTS |
Savings: $900 Cost: $2,700 |
$900 | 19,637 | - | - | - | - | - | - | - | - | - | - |
$900 19,637 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,200 Cost: $150 |
- | - | - | - | $1,200 | 309 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,200 309 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $1,197 Cost: $800 |
- | - | - | - | - | - | - | - | - | - | $1,197 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$1,197 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $430 Cost: $420 |
- | - | - | - | $430 | 107 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$430 107 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $380 Cost: - |
$260 | 5,569 | $120 | 28 | - | - | - | - | - | - | - | - |
$260 5,569 kWh |
$120 28 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $300 Cost: - |
- | - | - | - | - | - | $300 | 27,800 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$300 27,800 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,587 Cost: $14,940 |
$(-350) | (-7,619) | $5,720 | 1,290 | $7,590 | 1,947 | $300 | 27,800 | $(-1,870) | - | $1,197 | - | $(-350) (-7,619) kWh |
$5,720 1,290 kW-months/year |
$7,590 1,947 MMBtu |
$300 27,800 lb |
$(-1,870) - $ |
$1,197 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,007 Cost: $1,800 |
$(-1,250) | (-27,256) | $5,720 | 1,290 | $3,210 | 822 | - | - | $(-1,870) | - | $1,197 | - | $(-1,250) (-27,256) kWh |
$5,720 1,290 kW-months/year |
$3,210 822 MMBtu |
- - lb |
$(-1,870) - $ |
$1,197 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |