IAC Assessment: AM0288
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0288
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 1997
Principal Product Molded rubber products
NAICS n/a
SIC 3069 - Fabricated Rubber Products, Nec
Sales $1,000,000-$5,000,000
# of Employees 38
Plant Area (Sq.Ft.) 26,000
Annual Production 600,000 Pieces
Production Hrs. Annual 5,952
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $69,464 1,474,209 kWh $0.05
Electricity Demand $18,903 3,941 kW-months/year $4.80
Natural Gas $20,253 5,200 MMBtu $3.89
TOTAL ENERGY COSTS $108,620
RECOMMENDED SAVINGS* $12,587 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $7,007
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
01: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION Savings:
$2,220
Cost:
-
$(-1,510) (-32,825) $5,600 1,262 - - - - $(-1,870) - - - $(-1,510)
(-32,825)
kWh
$5,600
1,262
kW-months/year
-
-
MMBtu
-
-
lb
$(-1,870)
-
$
-
-
$
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$4,380
Cost:
$10,440
- - - - $4,380 1,125 - - - - - - -
-
kWh
-
-
kW-months/year
$4,380
1,125
MMBtu
-
-
lb
-
-
$
-
-
$
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$1,580
Cost:
$430
- - - - $1,580 406 - - - - - - -
-
kWh
-
-
kW-months/year
$1,580
406
MMBtu
-
-
lb
-
-
$
-
-
$
04: 2.7145 INSTALL SKYLIGHTS Savings:
$900
Cost:
$2,700
$900 19,637 - - - - - - - - - - $900
19,637
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,200
Cost:
$150
- - - - $1,200 309 - - - - - - -
-
kWh
-
-
kW-months/year
$1,200
309
MMBtu
-
-
lb
-
-
$
-
-
$
06: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$1,197
Cost:
$800
- - - - - - - - - - $1,197 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$1,197
-
$
07: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$430
Cost:
$420
- - - - $430 107 - - - - - - -
-
kWh
-
-
kW-months/year
$430
107
MMBtu
-
-
lb
-
-
$
-
-
$
08: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$380
Cost:
-
$260 5,569 $120 28 - - - - - - - - $260
5,569
kWh
$120
28
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
09: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$300
Cost:
-
- - - - - - $300 27,800 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$300
27,800
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$12,587
Cost:
$14,940
$(-350) (-7,619) $5,720 1,290 $7,590 1,947 $300 27,800 $(-1,870) - $1,197 - $(-350)
(-7,619)
kWh
$5,720
1,290
kW-months/year
$7,590
1,947
MMBtu
$300
27,800
lb
$(-1,870)
-
$
$1,197
-
$
TOTAL IMPLEMENTED Savings:
$7,007
Cost:
$1,800
$(-1,250) (-27,256) $5,720 1,290 $3,210 822 - - $(-1,870) - $1,197 - $(-1,250)
(-27,256)
kWh
$5,720
1,290
kW-months/year
$3,210
822
MMBtu
-
-
lb
$(-1,870)
-
$
$1,197
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes