Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 1998 |
Principal Product | Steel wire drawing, straight cut steel wire, welded wire mes |
NAICS | n/a |
SIC | 3315 - Steel Wire And Related Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 122 |
Plant Area (Sq.Ft.) | 103,700 |
Annual Production | 60,000 Tons |
Production Hrs. Annual | 8,544 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $160,353 | 5,783,705 | kWh | $0.03 |
Electricity Demand | $87,951 | 13,106 | kW-months/year | $6.71 |
TOTAL ENERGY COSTS | $273,504 | |||
RECOMMENDED SAVINGS* | $47,365 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $22,500 Cost: - |
- | - | - | - | - | - | $22,500 | 216,000 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$22,500 216,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $10,600 Cost: $150 |
- | - | - | - | - | - | $10,600 | 11,800 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$10,600 11,800 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $4,590 Cost: - |
- | - | - | - | - | - | $4,590 | 9,000 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$4,590 9,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,320 Cost: - |
$1,730 | 61,841 | $590 | 97 | - | - | - | - | - | - |
$1,730 61,841 kWh |
$590 97 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8112 COMBINE UTILITY METERS |
Savings: $2,310 Cost: $2,700 |
- | - | - | - | - | - | - | - | $2,310 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$2,310 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,595 Cost: $4,300 |
$1,200 | 42,790 | $395 | 65 | - | - | - | - | - | - |
$1,200 42,790 kWh |
$395 65 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.231 PURCHASE EQUIPMENT INSTEAD OF LEASING |
Savings: $1,420 Cost: $1,870 |
- | - | - | - | - | - | - | - | $1,420 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$1,420 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $1,260 Cost: - |
$1,260 | 45,135 | - | - | - | - | - | - | - | - |
$1,260 45,135 kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $520 Cost: $63 |
$460 | 7,034 | $60 | 10 | - | - | - | - | - | - |
$460 7,034 kWh |
$60 10 kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.6194 SHIP HYDRAULIC OIL TO SECONDARY FUEL PROGRAM |
Savings: $250 Cost: - |
- | - | - | - | $250 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$250 - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $47,365 Cost: $9,083 |
$4,650 | 156,800 | $1,045 | 172 | $250 | - | $37,690 | 236,800 | $3,730 | - | $4,650 156,800 kWh |
$1,045 172 kW-months/year |
$250 - gal |
$37,690 236,800 lb |
$3,730 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Solid Waste (non-haz) | Administrative Changes |