IAC Assessment: AM0596
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0596
IAC Center Texas A&M, College Station
Assessment Year 2011
Principal Product Multiplex machines
NAICS 339112 - Surgical and Medical Instrument Manufacturing
SIC 3842 - Surgical Appliances And Supplies
Sales $100,000,000-$500,000,000
# of Employees 300
Plant Area (Sq.Ft.) 32,000
Annual Production 900 Pieces
Production Hrs. Annual 3,120
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $162,254 3,018,495 kWh $0.05
Electricity Demand $95,113 7,238 kW-months/year $13.14
Electricity Fees $14,946 - $ -
TOTAL ENERGY COSTS $272,313
RECOMMENDED SAVINGS* $35,515 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $35,515
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$35,020
Cost:
-
- - - - $7,020 - - - $28,000 - -
-
kWh
-
-
kW-months/year
$7,020
-
$
-
-
$
$28,000
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$270
Cost:
$120
$40 740 $15 1 - - $215 - - - $40
740
kWh
$15
1
kW-months/year
-
-
$
$215
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$225
Cost:
$47
$185 3,390 $40 3 - - - - - - $185
3,390
kWh
$40
3
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$35,515
Cost:
$167
$225 4,130 $55 4 $7,020 - $215 - $28,000 - $225
4,130
kWh
$55
4
kW-months/year
$7,020
-
$
$215
-
$
$28,000
-
$
TOTAL IMPLEMENTED Savings:
$35,515
Cost:
$167
$225 4,130 $55 4 $7,020 - $215 - $28,000 - $225
4,130
kWh
$55
4
kW-months/year
$7,020
-
$
$215
-
$
$28,000
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost