Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2014 |
Principal Product | Automotive Chemicals |
NAICS | 325199 - All Other Basic Organic Chemical Manufacturing |
SIC | 2899 - Chemical Preparations, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 260 |
Plant Area (Sq.Ft.) | 265,000 |
Annual Production | 100,000,000 Pounds |
Production Hrs. Annual | 4,884 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $178,656 | 3,582,624 | kWh | $0.05 |
Electricity Demand | $61,564 | 10,394 | kW-months/year | $5.92 |
Electricity Fees | $1,629 | - | $ | - |
Natural Gas | $36,774 | 8,599 | MMBtu | $4.28 |
TOTAL ENERGY COSTS | $278,623 | |||
RECOMMENDED SAVINGS* | $28,660 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $24,740 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,615 Cost: $1,485 |
$6,790 | 130,615 | $1,825 | 321 | - | - | - | - | - | - | - | - | - | - |
$6,790 130,615 kWh |
$1,825 321 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,525 Cost: $400 |
$8,525 | 163,990 | - | - | - | - | - | - | - | - | - | - | - | - |
$8,525 163,990 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,180 Cost: $1,500 |
$1,715 | 33,300 | $465 | 82 | - | - | - | - | - | - | - | - | - | - |
$1,715 33,300 kWh |
$465 82 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,745 Cost: $735 |
$220 | 4,170 | $35 | 6 | - | - | - | - | $745 | - | $745 | - | - | - |
$220 4,170 kWh |
$35 6 kW-months/year |
- - $ |
- - MMBtu |
$745 - $ |
$745 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,725 Cost: $500 |
- | - | - | - | - | - | $1,725 | 400 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,725 400 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,950 Cost: - |
$1,350 | 26,000 | $600 | 106 | - | - | - | - | - | - | - | - | - | - |
$1,350 26,000 kWh |
$600 106 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $3,630 Cost: $1,452 |
- | - | - | - | $726 | - | - | - | - | - | - | - | $2,904 | - |
- - kWh |
- - kW-months/year |
$726 - $ |
- - MMBtu |
- - $ |
- - $ |
$2,904 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2123 INSULATE FEEDWATER TANK |
Savings: $290 Cost: $320 |
- | - | - | - | - | - | $290 | 52 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$290 52 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,660 Cost: $6,392 |
$18,600 | 358,075 | $2,925 | 515 | $726 | - | $2,015 | 452 | $745 | - | $745 | - | $2,904 | - | $18,600 358,075 kWh |
$2,925 515 kW-months/year |
$726 - $ |
$2,015 452 MMBtu |
$745 - $ |
$745 - $ |
$2,904 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $24,740 Cost: $4,620 |
$18,600 | 358,075 | $2,925 | 515 | - | - | $1,725 | 400 | $745 | - | $745 | - | - | - | $18,600 358,075 kWh |
$2,925 515 kW-months/year |
- - $ |
$1,725 400 MMBtu |
$745 - $ |
$745 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost |