IAC Assessment: AM0663
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0663
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2014
Principal Product All terrain oil industry vehicles
NAICS 336120 - Heavy Duty Truck Manufacturing
SIC 3711 - Motor Vehicles And Car Bodies
Sales $100,000,000-$500,000,000
# of Employees 200
Plant Area (Sq.Ft.) 56,000
Annual Production 120 Pieces
Production Hrs. Annual 3,175
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $90,672 1,581,360 kWh $0.06
Electricity Demand $76,212 6,887 kW-months/year $11.07
Electricity Fees $(-3,843) - $ -
TOTAL ENERGY COSTS $163,041
RECOMMENDED SAVINGS* $38,998 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,480
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$13,960
Cost:
$24,700
$8,200 143,000 $5,760 538 $8,200
143,000
kWh
$5,760
538
kW-months/year
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$9,000
Cost:
-
- - $9,000 840 -
-
kWh
$9,000
840
kW-months/year
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$5,730
Cost:
-
$5,730 100,000 - - $5,730
100,000
kWh
-
-
kW-months/year
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,790
Cost:
$55
$2,810 49,000 $1,980 185 $2,810
49,000
kWh
$1,980
185
kW-months/year
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$3,445
Cost:
-
$3,445 60,135 - - $3,445
60,135
kWh
-
-
kW-months/year
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$1,158
Cost:
$4,500
$495 6,005 $663 62 $495
6,005
kWh
$663
62
kW-months/year
07: 2.7145 INSTALL SKYLIGHTS Savings:
$915
Cost:
$4,140
$915 15,955 - - $915
15,955
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$38,998
Cost:
$33,395
$21,595 374,095 $17,403 1,625 $21,595
374,095
kWh
$17,403
1,625
kW-months/year
TOTAL IMPLEMENTED Savings:
$24,480
Cost:
$24,755
$16,740 292,000 $7,740 723 $16,740
292,000
kWh
$7,740
723
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand