IAC Assessment: AM0675
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AM0675
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Texas A&M, College Station
Assessment Year 2015
Principal Product angiography catheters
NAICS 339112 - Surgical and Medical Instrument Manufacturing
SIC 3841 - Surgical And Medical Instruments
Sales $10,000,000-$50,000,000
# of Employees 220
Plant Area (Sq.Ft.) 85,000
Annual Production 600,000 Pieces
Production Hrs. Annual 8,424
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $198,133 3,189,357 kWh $0.06
Electricity Demand $63,556 9,659 kW-months/year $6.58
Electricity Fees $20,763 - $ -
Natural Gas $39,208 3,689 MMBtu $10.63
TOTAL ENERGY COSTS $321,660
RECOMMENDED SAVINGS* $71,780 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $33,210
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$31,650
Cost:
$2,210
$25,900 454,000 $5,750 1,227 - - - - - - - - $25,900
454,000
kWh
$5,750
1,227
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
02: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$8,020
Cost:
$60
- - - - - - $8,020 1,160 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$8,020
1,160
MMBtu
-
-
lb
-
-
$
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$6,670
Cost:
$610
$5,960 104,570 $710 142 - - - - - - - - $5,960
104,570
kWh
$710
142
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
04: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,990
Cost:
-
- - - - - - - - $5,990 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$5,990
-
lb
-
-
$
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$4,250
Cost:
-
- - $4,250 848 - - - - - - - - -
-
kWh
$4,250
848
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
06: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$14,950
Cost:
$2,000
- - - - $2,990 - - - - - $11,960 - -
-
kWh
-
-
kW-months/year
$2,990
-
$
-
-
MMBtu
-
-
lb
$11,960
-
$
07: 2.2511 INSULATE BARE EQUIPMENT Savings:
$250
Cost:
$130
$250 4,400 - - - - - - - - - - $250
4,400
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
TOTAL RECOMMENDED Savings:
$71,780
Cost:
$5,010
$32,110 562,970 $10,710 2,217 $2,990 - $8,020 1,160 $5,990 - $11,960 - $32,110
562,970
kWh
$10,710
2,217
kW-months/year
$2,990
-
$
$8,020
1,160
MMBtu
$5,990
-
lb
$11,960
-
$
TOTAL IMPLEMENTED Savings:
$33,210
Cost:
$2,060
- - $4,250 848 $2,990 - $8,020 1,160 $5,990 - $11,960 - -
-
kWh
$4,250
848
kW-months/year
$2,990
-
$
$8,020
1,160
MMBtu
$5,990
-
lb
$11,960
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) One-time Revenue or Avoided Cost