IAC Assessment: AR0019
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AR0019
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Arkansas
Assessment Year 1994
Principal Product Inner Tubes & Bladders
NAICS n/a
SIC 3011 - Tires And Inner Tubes
Sales $10,000,000-$50,000,000
# of Employees 173
Plant Area (Sq.Ft.) 200,000
Annual Production 15,826,559 Pounds
Production Hrs. Annual 6,257
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $834,889 11,629,250 kWh $0.07
Natural Gas $264,498 88,496 MMBtu $2.99
TOTAL ENERGY COSTS $1,099,387
RECOMMENDED SAVINGS* $90,894 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $38,947
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$9,832
Cost:
$450
$9,832 136,870 - - $9,832
136,870
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,270
Cost:
$1,996
$4,270 59,496 - - $4,270
59,496
kWh
-
-
MMBtu
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$8,858
Cost:
$2,200
- - $8,858 2,962 -
-
kWh
$8,858
2,962
MMBtu
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$15,987
Cost:
$1,177
$15,987 222,743 - - $15,987
222,743
kWh
-
-
MMBtu
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$29,704
Cost:
-
$29,704 - - - $29,704
-
kWh
-
-
MMBtu
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$22,243
Cost:
$47,000
$22,243 309,789 - - $22,243
309,789
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$90,894
Cost:
$52,823
$82,036 728,898 $8,858 2,962 $82,036
728,898
kWh
$8,858
2,962
MMBtu
TOTAL IMPLEMENTED Savings:
$38,947
Cost:
$5,823
$30,089 419,109 $8,858 2,962 $30,089
419,109
kWh
$8,858
2,962
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas