Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Arkansas |
---|---|
Assessment Year | 1996 |
Principal Product | Fiberglass Tubing |
NAICS | n/a |
SIC | 3084 - Plastics Pipe |
Sales | $1,000,000-$5,000,000 |
# of Employees | 30 |
Plant Area (Sq.Ft.) | 48,400 |
Annual Production | 80,290 Thousand Feet |
Production Hrs. Annual | 3,441 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $23,224 | 467,761 | kWh | $0.05 |
Electricity Demand | $15,874 | 1,660 | kW-months/year | $9.56 |
Natural Gas | $12,011 | 2,730 | MMBtu | $4.40 |
TOTAL ENERGY COSTS | $60,941 | |||
RECOMMENDED SAVINGS* | $19,140 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $19,140 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Electricity Usage | Electricity Demand | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $7,955 Cost: $1,631 |
$3,119 | 84,994 | $4,836 | 351 | - | - |
$3,119 84,994 kWh |
$4,836 351 kW-months/year |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,513 Cost: $477 |
$1,156 | 30,481 | $1,357 | 100 | - | - |
$1,156 30,481 kWh |
$1,357 100 kW-months/year |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,384 Cost: $4,700 |
$2,888 | 44,256 | $1,496 | 143 | - | - |
$2,888 44,256 kWh |
$1,496 143 kW-months/year |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $608 Cost: $80 |
$258 | 7,913 | $350 | 25 | - | - |
$258 7,913 kWh |
$350 25 kW-months/year |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,100 Cost: $70 |
$444 | 13,482 | $656 | 47 | - | - |
$444 13,482 kWh |
$656 47 kW-months/year |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.7311 MAINTAIN MACHINES TO REDUCE LEAKS |
Savings: $2,580 Cost: $100 |
- | - | - | - | $2,580 | 180 |
- - kWh |
- - kW-months/year |
$2,580 180 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,140 Cost: $7,058 |
$7,865 | 181,126 | $8,695 | 666 | $2,580 | 180 | $7,865 181,126 kWh |
$8,695 666 kW-months/year |
$2,580 180 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $19,140 Cost: $7,058 |
$7,865 | 181,126 | $8,695 | 666 | $2,580 | 180 | $7,865 181,126 kWh |
$8,695 666 kW-months/year |
$2,580 180 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Electricity Usage | Electricity Demand | Other Liquid (haz) |