Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Arkansas |
---|---|
Assessment Year | 1997 |
Principal Product | Peanut Butter |
NAICS | n/a |
SIC | 2099 - Food Preparations, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 143,000 |
Annual Production | 127,000,000 Pounds |
Production Hrs. Annual | 6,497 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $354,995 | 16,415,006 | kWh | $0.02 |
Electricity Demand | $592,302 | 33,750 | kW-months/year | $17.55 |
Natural Gas | $114,906 | 32,612 | MMBtu | $3.52 |
TOTAL ENERGY COSTS | $1,001,375 | |||
RECOMMENDED SAVINGS* | $101,192 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,438 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $20,039 Cost: $1,110 |
$20,039 | 360,492 | - | - | - | - |
$20,039 360,492 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,439 Cost: $3,524 |
$2,439 | 7,913 | - | - | - | - |
$2,439 7,913 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,961 Cost: - |
$2,961 | 59,789 | - | - | - | - |
$2,961 59,789 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,406 Cost: $500 |
$1,406 | 36,635 | - | - | - | - |
$1,406 36,635 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $907 Cost: $90 |
$907 | 23,740 | - | - | - | - |
$907 23,740 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3136 OVERLAP CUSTODIAL SERVICES WITH NORMAL DAY HOURS |
Savings: $498 Cost: - |
$498 | 22,567 | - | - | - | - |
$498 22,567 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $48,811 Cost: $10,230 |
- | - | $48,811 | 84,448 | - | - |
- - kWh |
$48,811 84,448 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $20,099 Cost: $16,000 |
- | - | $20,099 | 29,268 | - | - |
- - kWh |
$20,099 29,268 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $4,032 Cost: $21,600 |
- | - | - | - | $4,032 | - |
- - kWh |
- - lb |
$4,032 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $101,192 Cost: $53,054 |
$28,250 | 511,136 | $68,910 | 113,716 | $4,032 | - | $28,250 511,136 kWh |
$68,910 113,716 lb |
$4,032 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,438 Cost: $41,214 |
$6,307 | 91,442 | $20,099 | 29,268 | $4,032 | - | $6,307 91,442 kWh |
$20,099 29,268 lb |
$4,032 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes |