IAC logo
IAC Assessment: AS0001
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0001
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 1990
Principal Product PLASTIC BOTTLES
NAICS n/a
SIC 3085 - Plastics Bottles
Sales $10,000,000-$50,000,000
# of Employees 96
Plant Area (Sq.Ft.) 0
Annual Production 111,000,000 Pieces
Production Hrs. Annual 8,736
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $797,745 14,269,930 kWh $0.06
TOTAL ENERGY COSTS $797,745
RECOMMENDED SAVINGS* $12,425 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,136
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$895
Cost:
$1,483
$895 16,120 $895
16,120
kWh
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$3,168
Cost:
$500
$3,168 56,858 $3,168
56,858
kWh
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,710
Cost:
-
$2,710 48,652 $2,710
48,652
kWh
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,289
Cost:
$656
$2,289 41,032 $2,289
41,032
kWh
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,764
Cost:
$1,440
$1,764 31,653 $1,764
31,653
kWh
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$882
Cost:
$1,800
$882 15,826 $882
15,826
kWh
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$717
Cost:
$250
$717 12,896 $717
12,896
kWh
TOTAL RECOMMENDED Savings:
$12,425
Cost:
$6,129
$12,425 223,037 $12,425
223,037
kWh
TOTAL IMPLEMENTED Savings:
$10,136
Cost:
$5,473
$10,136 182,005 $10,136
182,005
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage