Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 1993 |
Principal Product | AIRCRAFT SEATING |
NAICS | n/a |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 2,700 Pieces |
Production Hrs. Annual | 3,900 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $146,851 | 1,948,124 | kWh | $0.08 |
Natural Gas | $2,085 | 180 | MMBtu | $11.58 |
TOTAL ENERGY COSTS | $148,936 | |||
RECOMMENDED SAVINGS* | $58,290 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,332 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $27,862 Cost: $65,800 |
$35,855 | 381,594 | $(-7,993) | (-1,628) | - | - |
$35,855 381,594 kWh |
$(-7,993) (-1,628) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $606 Cost: - |
$660 | 8,792 | - | - | $(-54) | - |
$660 8,792 kWh |
- - MMBtu |
$(-54) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,612 Cost: $12,391 |
$3,612 | 48,066 | - | - | - | - |
$3,612 48,066 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $557 Cost: $2,128 |
$557 | 7,327 | - | - | - | - |
$557 7,327 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $137 Cost: $250 |
$137 | 1,758 | - | - | - | - |
$137 1,758 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $1,339 Cost: $2,035 |
$1,339 | 17,585 | - | - | - | - |
$1,339 17,585 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $2,191 Cost: $4,400 |
$2,191 | 29,015 | - | - | - | - |
$2,191 29,015 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $15,260 Cost: $18,920 |
$15,260 | 202,521 | - | - | - | - |
$15,260 202,521 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $6,126 Cost: - |
$6,126 | 81,184 | - | - | - | - |
$6,126 81,184 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $219 Cost: $329 |
$219 | 2,931 | - | - | - | - |
$219 2,931 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $381 Cost: - |
$381 | 4,982 | - | - | - | - |
$381 4,982 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $58,290 Cost: $106,253 |
$66,337 | 785,755 | $(-7,993) | (-1,628) | $(-54) | - | $66,337 785,755 kWh |
$(-7,993) (-1,628) MMBtu |
$(-54) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,332 Cost: $329 |
$7,386 | 97,889 | - | - | $(-54) | - | $7,386 97,889 kWh |
- - MMBtu |
$(-54) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |