IAC Assessment: AS0275
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0275
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2000
Principal Product Electronics
NAICS n/a
SIC 3629 - Electrical Industrial Apparatus, Nec
Sales $10,000,000-$50,000,000
# of Employees 125
Plant Area (Sq.Ft.) 50,000
Annual Production 180,000 Pieces
Production Hrs. Annual 4,000
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $87,713 1,383,646 kWh $0.06
Electricity Demand $31,876 4,126 kW-months/year $7.73
Electricity Fees $6,164 - $ -
Natural Gas $13,770 2,055 MMBtu $6.70
TOTAL ENERGY COSTS $145,524
RECOMMENDED SAVINGS* $58,595 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Water Disposal Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ Tgal $ $ $ $ $ $
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$367
Cost:
$380
$279 4,396 $88 13 - - - - - - - - $279
4,396
kWh
$88
13
kW-months/year
-
-
Tgal
-
-
$
-
-
$
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,665
Cost:
$2,256
$1,267 19,343 $398 67 - - - - - - - - $1,267
19,343
kWh
$398
67
kW-months/year
-
-
Tgal
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$477
Cost:
$544
$286 4,396 $35 5 - - $78 - - - $78 - $286
4,396
kWh
$35
5
kW-months/year
-
-
Tgal
$78
-
$
-
-
$
$78
-
$
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$981
Cost:
$272
$981 14,947 - - - - - - - - - - $981
14,947
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
-
-
$
-
-
$
05: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE Savings:
$2,017
Cost:
$120
- - - - $2,017 725,600 - - - - - - -
-
kWh
-
-
kW-months/year
$2,017
725,600
Tgal
-
-
$
-
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$588
Cost:
$60
- - - - - - - - $588 - - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
$588
-
$
-
-
$
07: 4.452 ELIMINATE SHIFT Savings:
$52,500
Cost:
$16,000
- - - - - - $52,500 - - - - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
$52,500
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$58,595
Cost:
$19,632
$2,813 43,082 $521 85 $2,017 725,600 $52,578 - $588 - $78 - $2,813
43,082
kWh
$521
85
kW-months/year
$2,017
725,600
Tgal
$52,578
-
$
$588
-
$
$78
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ $ $ $ $ $
Electricity Usage Electricity Demand Water Disposal Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Water Disposal Personnel Changes Administrative Changes Ancillary Material Cost