IAC logo
IAC Assessment: AS0286
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0286
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2000
Principal Product Flat Circuits and Flex board
NAICS n/a
SIC 3678 - Electronic Connectors
Sales $100,000,000-$500,000,000
# of Employees 300
Plant Area (Sq.Ft.) 150,000
Annual Production 100,000 Pieces
Production Hrs. Annual 8,568
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $772,676 16,445,194 kWh $0.05
Electricity Fees $140,854 - $ -
Natural Gas $132,086 23,111 MMBtu $5.72
TOTAL ENERGY COSTS $1,316,468
RECOMMENDED SAVINGS* $37,507 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ gal $ lb $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,045
Cost:
$382
$3,645 115,182 $400 161 - - - - - - - - - - $3,645
115,182
kWh
$400
161
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$6,469
Cost:
$3,800
$5,814 183,763 $655 264 - - - - - - - - - - $5,814
183,763
kWh
$655
264
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$4,073
Cost:
$6,959
$3,711 104,338 $362 146 - - - - - - - - - - $3,711
104,338
kWh
$362
146
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$407
Cost:
$609
$217 6,741 $17 7 - - - - $86 - - - $87 - $217
6,741
kWh
$17
7
kW-months/year
-
-
gal
-
-
lb
$86
-
$
-
-
$
$87
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$10,262
Cost:
$120
$10,262 324,736 - - - - - - - - - - - - $10,262
324,736
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$1,244
Cost:
$120
- - - - - - - - - - $1,244 - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
$1,244
-
$
-
-
$
07: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$576
Cost:
$60
- - - - - - $576 - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
$576
-
lb
-
-
$
-
-
$
-
-
$
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE Savings:
$4,509
Cost:
$780
- - - - $5,836 3,857 - - $(-1,327) - - - - - -
-
kWh
-
-
kW-months/year
$5,836
3,857
gal
-
-
lb
$(-1,327)
-
$
-
-
$
-
-
$
09: 4.446 AUTOMATE FINISHING PROCESS Savings:
$5,355
Cost:
$1,500
- - - - - - - - $5,355 - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
$5,355
-
$
-
-
$
-
-
$
10: 4.454 MODIFY STARTUP/SHUTDOWN TIMES Savings:
$567
Cost:
$120
- - - - - - - - - - $567 - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
$567
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$37,507
Cost:
$14,450
$23,649 734,760 $1,434 578 $5,836 3,857 $576 - $4,114 - $1,811 - $87 - $23,649
734,760
kWh
$1,434
578
kW-months/year
$5,836
3,857
gal
$576
-
lb
$4,114
-
$
$1,811
-
$
$87
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ lb $ $ $ $ $ $
Electricity Usage Electricity Demand Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost