IAC Assessment: AS0364
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0364
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2003
Principal Product Wood Moulding
NAICS 321918 - Other Millwork (including Flooring)
SIC 2431 - Millwork
Sales $5,000,000-$10,000,000
# of Employees 50
Plant Area (Sq.Ft.) 0
Annual Production 14,688 Thousand Feet
Production Hrs. Annual 2,134
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $94,269 1,084,700 kWh $0.09
Electricity Demand $10,887 6,696 kW-months/year $1.63
Electricity Fees $7,065 - $ -
TOTAL ENERGY COSTS $112,221
RECOMMENDED SAVINGS* $12,134 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost
$ kWh $ kW-months/year $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,347
Cost:
$7,928
$852 11,737 $338 66 $157 - $852
11,737
kWh
$338
66
kW-months/year
$157
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$221
Cost:
$524
$168 2,313 $53 11 - - $168
2,313
kWh
$53
11
kW-months/year
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$990
Cost:
$150
$725 9,974 $265 52 - - $725
9,974
kWh
$265
52
kW-months/year
-
-
$
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$9,291
Cost:
$31,527
$7,053 97,144 $2,238 546 - - $7,053
97,144
kWh
$2,238
546
kW-months/year
-
-
$
05: 2.7314 REDUCE VENTILATION AIR Savings:
$285
Cost:
$10
$204 2,809 $81 16 - - $204
2,809
kWh
$81
16
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$12,134
Cost:
$40,139
$9,002 123,977 $2,975 691 $157 - $9,002
123,977
kWh
$2,975
691
kW-months/year
$157
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost