IAC Assessment: AS0367
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0367
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2004
Principal Product Citrus Juices
NAICS 311421 - Fruit and Vegetable Canning
SIC 2033 - Canned Fruits And Vegetables
Sales $10,000,000-$50,000,000
# of Employees 65
Plant Area (Sq.Ft.) 40,000
Annual Production 2,000 Thousand Gallons
Production Hrs. Annual 7,344
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $103,629 1,790,400 kWh $0.06
Electricity Demand $11,142 4,385 kW-months/year $2.54
Electricity Fees $8,314 - $ -
Natural Gas $24,396 4,214 MMBtu $5.79
TOTAL ENERGY COSTS $199,976
RECOMMENDED SAVINGS* $57,349 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $14,811
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT Savings:
$14,811
Cost:
$5,240
- - - - $14,811 2,664 - - -
-
kWh
-
-
kW-months/year
$14,811
2,664
MMBtu
-
-
$
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$36,297
Cost:
$90,000
$103,629 1,790,000 $11,142 4,385 $(-78,474) (-14,114) - - $103,629
1,790,000
kWh
$11,142
4,385
kW-months/year
$(-78,474)
(-14,114)
MMBtu
-
-
$
03: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES Savings:
$3,275
Cost:
$4,395
- - - - $3,275 589 - - -
-
kWh
-
-
kW-months/year
$3,275
589
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,352
Cost:
$9,037
$577 14,582 $352 43 - - $423 - $577
14,582
kWh
$352
43
kW-months/year
-
-
MMBtu
$423
-
$
05: 2.7145 INSTALL SKYLIGHTS Savings:
$708
Cost:
$3,395
$708 17,885 - - - - - - $708
17,885
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$567
Cost:
$1,500
$299 7,552 $268 33 - - - - $299
7,552
kWh
$268
33
kW-months/year
-
-
MMBtu
-
-
$
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$339
Cost:
$460
$279 7,045 $60 7 - - - - $279
7,045
kWh
$60
7
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$57,349
Cost:
$114,027
$105,492 1,837,064 $11,822 4,468 $(-60,388) (-10,861) $423 - $105,492
1,837,064
kWh
$11,822
4,468
kW-months/year
$(-60,388)
(-10,861)
MMBtu
$423
-
$
TOTAL IMPLEMENTED Savings:
$14,811
Cost:
$5,240
- - - - $14,811 2,664 - - -
-
kWh
-
-
kW-months/year
$14,811
2,664
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost