Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2004 |
Principal Product | Wire Mesh Products |
NAICS | 332812 - Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479 - Metal Coating And Allied Services |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 1,224,000 Pieces |
Production Hrs. Annual | 4,182 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $196,665 | 2,729,460 | kWh | $0.07 |
Electricity Demand | $17,891 | 1,112 | kW-months/year | $16.09 |
Electricity Fees | $16,494 | - | $ | - |
Natural Gas | $105,011 | 13,344 | MMBtu | $7.87 |
TOTAL ENERGY COSTS | $336,061 | |||
RECOMMENDED SAVINGS* | $165,993 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3312 INSTALL EFFICIENT RECTIFIERS |
Savings: $79,520 Cost: $51,660 |
$69,615 | 1,506,810 | $9,905 | 2,232 | - | - | - | - | - | - |
$69,615 1,506,810 kWh |
$9,905 2,232 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.453 RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION |
Savings: $66,870 Cost: $4,565 |
- | - | - | - | - | - | $10,413 | - | $56,457 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$10,413 - $ |
$56,457 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $7,943 Cost: $52,000 |
$5,120 | 110,823 | $2,823 | 636 | - | - | - | - | - | - |
$5,120 110,823 kWh |
$2,823 636 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $4,650 Cost: $2,800 |
$3,798 | 82,218 | $852 | 240 | - | - | - | - | - | - |
$3,798 82,218 kWh |
$852 240 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,789 Cost: $5,720 |
- | - | - | - | $3,789 | 487 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,789 487 MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,743 Cost: $15 |
$1,631 | 35,309 | $112 | 24 | - | - | - | - | - | - |
$1,631 35,309 kWh |
$112 24 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,286 Cost: $7,980 |
$895 | 19,382 | $391 | 88 | - | - | - | - | - | - |
$895 19,382 kWh |
$391 88 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $192 Cost: $199 |
$150 | 3,327 | $42 | 9 | - | - | - | - | - | - |
$150 3,327 kWh |
$42 9 kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $165,993 Cost: $124,939 |
$81,209 | 1,757,869 | $14,125 | 3,229 | $3,789 | 487 | $10,413 | - | $56,457 | - | $81,209 1,757,869 kWh |
$14,125 3,229 kW-months/year |
$3,789 487 MMBtu |
$10,413 - $ |
$56,457 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Increase in Production |