Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2004 |
Principal Product | Printed Circuit Boards |
NAICS | 334412 - Bare Printed Circuit Board Manufacturing |
SIC | 3672 - Printed Circuit Boards |
Sales | $50,000,000-$100,000,000 |
# of Employees | 720 |
Plant Area (Sq.Ft.) | 275,000 |
Annual Production | 208,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,374,167 | 24,255,291 | kWh | $0.06 |
Electricity Fees | $212,130 | - | $ | - |
Natural Gas | $212,130 | 32,236 | MMBtu | $6.58 |
TOTAL ENERGY COSTS | $2,447,824 | |||
RECOMMENDED SAVINGS* | $212,073 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $87,632 Cost: $105,000 |
$74,790 | 1,350,000 | $12,842 | 2,640 | - | - |
$74,790 1,350,000 kWh |
$12,842 2,640 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $62,038 Cost: $22,800 |
$46,395 | 1,220,132 | $15,643 | 1,956 | - | - |
$46,395 1,220,132 kWh |
$15,643 1,956 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2165 SUBSTITUTE AIR FOR STEAM TO ATOMIZE OIL |
Savings: $17,943 Cost: $12,000 |
- | - | - | - | $17,943 | 3,028 |
- - kWh |
- - kW-months/year |
$17,943 3,028 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $12,453 Cost: $7,000 |
$7,335 | 152,229 | $5,118 | 665 | - | - |
$7,335 152,229 kWh |
$5,118 665 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,040 Cost: $45,048 |
$7,949 | 162,980 | $2,091 | 277 | - | - |
$7,949 162,980 kWh |
$2,091 277 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $12,176 Cost: $60 |
$7,473 | 219,154 | $4,703 | 352 | - | - |
$7,473 219,154 kWh |
$4,703 352 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,938 Cost: $144 |
$3,795 | 111,378 | $3,143 | 284 | - | - |
$3,795 111,378 kWh |
$3,143 284 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,853 Cost: $4,125 |
$2,853 | 51,506 | - | - | - | - |
$2,853 51,506 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $212,073 Cost: $196,177 |
$150,590 | 3,267,379 | $43,540 | 6,174 | $17,943 | 3,028 | $150,590 3,267,379 kWh |
$43,540 6,174 kW-months/year |
$17,943 3,028 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |