Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2004 |
Principal Product | Heat Treating |
NAICS | 332811 - Metal Heat Treating |
SIC | 3398 - Metal Heat Treating |
Sales | $1,000,000-$5,000,000 |
# of Employees | 43 |
Plant Area (Sq.Ft.) | 42,000 |
Annual Production | 10,000 Pieces |
Production Hrs. Annual | 7,467 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $305,342 | 4,825,000 | kWh | $0.06 |
Electricity Demand | $21,110 | 13,190 | kW-months/year | $1.60 |
Electricity Fees | $24,719 | - | $ | - |
Natural Gas | $230,225 | 34,258 | MMBtu | $6.72 |
TOTAL ENERGY COSTS | $581,396 | |||
RECOMMENDED SAVINGS* | $32,713 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,560 Cost: $8,230 |
$914 | 19,793 | $203 | 46 | - | - | $443 | - |
$914 19,793 kWh |
$203 46 kW-months/year |
- - MMBtu |
$443 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $504 Cost: $456 |
$437 | 9,457 | $67 | 15 | - | - | - | - |
$437 9,457 kWh |
$67 15 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $337 Cost: $1,400 |
$240 | 5,191 | $97 | 22 | - | - | - | - |
$240 5,191 kWh |
$97 22 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $28,518 Cost: $60,100 |
$34,499 | 746,700 | $10,632 | 2,400 | $(-16,613) | (-2,548) | - | - |
$34,499 746,700 kWh |
$10,632 2,400 kW-months/year |
$(-16,613) (-2,548) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $1,794 Cost: $3,500 |
- | - | - | - | $1,794 | 275 | - | - |
- - kWh |
- - kW-months/year |
$1,794 275 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,713 Cost: $73,686 |
$36,090 | 781,141 | $10,999 | 2,483 | $(-14,819) | (-2,273) | $443 | - | $36,090 781,141 kWh |
$10,999 2,483 kW-months/year |
$(-14,819) (-2,273) MMBtu |
$443 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |