Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2004 |
Principal Product | Packaged Salad |
NAICS | 311991 - Perishable Prepared Food Manufacturing |
SIC | 2099 - Food Preparations, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 225,000 |
Annual Production | 13,000,000 Pieces |
Production Hrs. Annual | 6,489 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $646,120 | 11,450,100 | kWh | $0.06 |
Electricity Demand | $41,538 | 25,550 | kW-months/year | $1.63 |
Electricity Fees | $62,650 | - | $ | - |
TOTAL ENERGY COSTS | $750,308 | |||
RECOMMENDED SAVINGS* | $3,315,434 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $43,207 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $34,302 Cost: $480 |
$29,114 | 622,087 | $5,188 | 1,150 | - | - |
$29,114 622,087 kWh |
$5,188 1,150 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $3,270,456 Cost: $3,624,320 |
- | - | - | - | $3,270,456 | - |
- - kWh |
- - kW-months/year |
$3,270,456 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $1,133 Cost: $506 |
$1,133 | 24,204 | - | - | - | - |
$1,133 24,204 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $2,081 Cost: $499 |
$1,766 | 37,728 | $315 | 70 | - | - |
$1,766 37,728 kWh |
$315 70 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $638 Cost: $360 |
$521 | 11,137 | $117 | 26 | - | - |
$521 11,137 kWh |
$117 26 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,918 Cost: $12,008 |
$2,477 | 52,931 | $441 | 98 | - | - |
$2,477 52,931 kWh |
$441 98 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $3,906 Cost: $6,178 |
$3,282 | 70,136 | $624 | 138 | - | - |
$3,282 70,136 kWh |
$624 138 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $3,315,434 Cost: $3,644,351 |
$38,293 | 818,223 | $6,685 | 1,482 | $3,270,456 | - | $38,293 818,223 kWh |
$6,685 1,482 kW-months/year |
$3,270,456 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $43,207 Cost: $19,165 |
$36,639 | 782,882 | $6,568 | 1,456 | - | - | $36,639 782,882 kWh |
$6,568 1,456 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |