Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2005 |
Principal Product | Food products, snacks |
NAICS | 311919 - Other Snack Food Manufacturing |
SIC | 2099 - Food Preparations, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 128,000 |
Annual Production | 18,500,000 Pounds |
Production Hrs. Annual | 7,344 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $196,150 | 3,452,800 | kWh | $0.06 |
Electricity Demand | $11,242 | 6,992 | kW-months/year | $1.61 |
Electricity Fees | $17,034 | - | $ | - |
Natural Gas | $271,769 | 59,622 | MMBtu | $4.56 |
TOTAL ENERGY COSTS | $496,195 | |||
RECOMMENDED SAVINGS* | $30,307 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $19,864 Cost: $15,000 |
$19,391 | 341,329 | $473 | 294 | - | - | - | - |
$19,391 341,329 kWh |
$473 294 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $7,302 Cost: $1,000 |
$7,033 | 72,550 | $269 | 105 | - | - | - | - |
$7,033 72,550 kWh |
$269 105 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,147 Cost: $6,757 |
$2,066 | 35,388 | $81 | 50 | - | - | - | - |
$2,066 35,388 kWh |
$81 50 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $474 Cost: $150 |
- | - | - | - | - | - | $474 | 14,189 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$474 14,189 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $520 Cost: $250 |
- | - | - | - | $520 | 114 | - | - |
- - kWh |
- - kW-months/year |
$520 114 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,307 Cost: $23,157 |
$28,490 | 449,267 | $823 | 449 | $520 | 114 | $474 | 14,189 | $28,490 449,267 kWh |
$823 449 kW-months/year |
$520 114 MMBtu |
$474 14,189 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) |