Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2006 |
Principal Product | Printed circuit boards |
NAICS | 334412 - Bare Printed Circuit Board Manufacturing |
SIC | 3672 - Printed Circuit Boards |
Sales | $50,000,000-$100,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 8,760 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $697,736 | 6,679,462 | kWh | $0.10 |
Electricity Demand | $61,550 | 5,796 | kW-months/year | $10.62 |
Natural Gas | $28,886 | 31,921 | MMBtu | $0.90 |
TOTAL ENERGY COSTS | $788,172 | |||
RECOMMENDED SAVINGS* | $61,613 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,850 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $10,102 Cost: $17,458 |
$2,463 | 23,568 | $7,639 | 673 | - | - |
$2,463 23,568 kWh |
$7,639 673 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $9,823 Cost: $500 |
$8,282 | 79,250 | $1,541 | 144 | - | - |
$8,282 79,250 kWh |
$1,541 144 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $8,267 Cost: $2,077 |
- | - | - | - | $8,267 | 214 |
- - kWh |
- - kW-months/year |
$8,267 214 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $7,727 Cost: $5,500 |
$6,514 | 62,332 | $1,213 | 114 | - | - |
$6,514 62,332 kWh |
$1,213 114 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $6,172 Cost: $2,000 |
$4,441 | 42,502 | $1,731 | 163 | - | - |
$4,441 42,502 kWh |
$1,731 163 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,221 Cost: $1,000 |
$5,221 | 49,962 | - | - | - | - |
$5,221 49,962 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,539 Cost: $15,085 |
$6,309 | 60,393 | $1,230 | 115 | - | - |
$6,309 60,393 kWh |
$1,230 115 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $3,590 Cost: $20,832 |
$3,009 | 28,796 | $581 | 55 | - | - |
$3,009 28,796 kWh |
$581 55 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.9112 USE SOLAR HEAT TO HEAT WATER |
Savings: $3,172 Cost: $14,400 |
$3,136 | 4,801 | $36 | 3 | - | - |
$3,136 4,801 kWh |
$36 3 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $61,613 Cost: $78,852 |
$39,375 | 351,604 | $13,971 | 1,267 | $8,267 | 214 | $39,375 351,604 kWh |
$13,971 1,267 kW-months/year |
$8,267 214 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,850 Cost: $18,662 |
$19,812 | 189,605 | $2,771 | 259 | $8,267 | 214 | $19,812 189,605 kWh |
$2,771 259 kW-months/year |
$8,267 214 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |