Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2022 |
Principal Product | Recycled Plastic Products |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 153,969 |
Annual Production | 12,300,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,450,061 | 30,838,665 | kWh | $0.05 |
Electricity Demand | $785,019 | 86,611 | kW-months/year | $9.06 |
Electricity Fees | $110,243 | - | $ | - |
TOTAL ENERGY COSTS | $2,345,323 | |||
RECOMMENDED SAVINGS* | $92,731 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $29,267 Cost: $226,584 |
$(-18,733) | (-398,571) | - | - | $36,000 | 1,333 | - | - | $12,000 | - |
$(-18,733) (-398,571) kWh |
- - kW-months/year |
$36,000 1,333 gal |
- - $ |
$12,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $22,746 Cost: $3,707 |
$17,987 | 382,701 | $4,759 | 524 | - | - | - | - | - | - |
$17,987 382,701 kWh |
$4,759 524 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $21,371 Cost: $9,286 |
$19,622 | 417,498 | $1,749 | 193 | - | - | - | - | - | - |
$19,622 417,498 kWh |
$1,749 193 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $16,536 Cost: $3,537 |
$11,560 | 245,943 | $4,976 | 548 | - | - | - | - | - | - |
$11,560 245,943 kWh |
$4,976 548 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,420 Cost: $3,762 |
$1,240 | 26,419 | $504 | 56 | - | - | $676 | - | - | - |
$1,240 26,419 kWh |
$504 56 kW-months/year |
- - gal |
$676 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3135 SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS |
Savings: $391 Cost: $1,619 |
- | - | $391 | 43 | - | - | - | - | - | - |
- - kWh |
$391 43 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $92,731 Cost: $248,495 |
$31,676 | 673,990 | $12,379 | 1,364 | $36,000 | 1,333 | $676 | - | $12,000 | - | $31,676 673,990 kWh |
$12,379 1,364 kW-months/year |
$36,000 1,333 gal |
$676 - $ |
$12,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Ancillary Material Cost | One-time Revenue or Avoided Cost |