IAC Assessment: AS0538
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0538
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2022
Principal Product 200mm silicon wafers
NAICS 334413 - Semiconductor and Related Device Manufacturing
SIC 3674 - Semiconductors And Related Devices
Sales $100,000,000-$500,000,000
# of Employees 390
Plant Area (Sq.Ft.) 1,500,000
Annual Production 2,940,000 Units
Production Hrs. Annual 8,760
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $2,319,821 74,452,000 kWh $0.03
Electricity Demand $1,752,987 220,310 kW-months/year $7.96
Electricity Fees $1,398,044 - $ -
Natural Gas $437,752 58,686 MMBtu $7.46
TOTAL ENERGY COSTS $5,908,604
RECOMMENDED SAVINGS* $1,288,923 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$722,230
Cost:
$2,223,000
$579,237 18,565,298 $142,993 17,964 - - - - $579,237
18,565,298
kWh
$142,993
17,964
kW-months/year
-
-
MMBtu
-
-
$
02: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) Savings:
$290,625
Cost:
$126,000
- - - - $290,625 38,750 - - -
-
kWh
-
-
kW-months/year
$290,625
38,750
MMBtu
-
-
$
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$170,279
Cost:
$17,076
$81,302 2,605,820 $88,977 11,178 - - - - $81,302
2,605,820
kWh
$88,977
11,178
kW-months/year
-
-
MMBtu
-
-
$
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$99,703
Cost:
$442,407
$47,605 1,525,803 $52,098 6,545 - - - - $47,605
1,525,803
kWh
$52,098
6,545
kW-months/year
-
-
MMBtu
-
-
$
05: 2.7134 USE PHOTOCELL CONTROLS Savings:
$3,648
Cost:
$8,619
$2,733 87,600 $915 115 - - - - $2,733
87,600
kWh
$915
115
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,438
Cost:
$3,603
$1,627 52,114 $454 57 - - $357 - $1,627
52,114
kWh
$454
57
kW-months/year
-
-
MMBtu
$357
-
$
TOTAL RECOMMENDED Savings:
$1,288,923
Cost:
$2,820,705
$712,504 22,836,635 $285,437 35,859 $290,625 38,750 $357 - $712,504
22,836,635
kWh
$285,437
35,859
kW-months/year
$290,625
38,750
MMBtu
$357
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost