Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2024 |
Principal Product | Portland Cement |
NAICS | 327310 - Cement Manufacturing |
SIC | 3241 - Cement, Hydraulic |
Sales | $50,000,000-$100,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 1,336,000 |
Annual Production | 660,000 Tons |
Production Hrs. Annual | 8,760 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $3,777,130 | 85,896,950 | kWh | $0.04 |
Electricity Demand | $1,749,688 | 298,923 | kW-months/year | $5.85 |
Electricity Fees | $24,567 | - | $ | - |
Natural Gas | $5,718,157 | 1,794,636 | MMBtu | $3.19 |
TOTAL ENERGY COSTS | $11,269,542 | |||
RECOMMENDED SAVINGS* | $188,249 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $81,526 Cost: $55,952 |
$68,962 | 1,567,337 | $12,564 | 2,148 | - | - | - | - | - | - |
$68,962 1,567,337 kWh |
$12,564 2,148 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $61,102 Cost: $20,000 |
$51,688 | 1,174,716 | $9,414 | 1,609 | - | - | - | - | - | - |
$51,688 1,174,716 kWh |
$9,414 1,609 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $22,882 Cost: $38 |
- | - | - | - | - | - | - | - | $22,882 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$22,882 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,525 Cost: $34,427 |
$17,070 | 387,933 | $3,108 | 531 | - | - | $(-3,653) | - | - | - |
$17,070 387,933 kWh |
$3,108 531 kW-months/year |
- - $ |
$(-3,653) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $5,292 Cost: $908 |
- | - | - | - | - | - | - | - | $5,292 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$5,292 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $492 Cost: $511 |
- | - | - | - | $492 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$492 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $430 Cost: $987 |
$430 | 9,780 | - | - | - | - | - | - | - | - |
$430 9,780 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $188,249 Cost: $112,823 |
$138,150 | 3,139,766 | $25,086 | 4,288 | $492 | - | $(-3,653) | - | $28,174 | - | $138,150 3,139,766 kWh |
$25,086 4,288 kW-months/year |
$492 - $ |
$(-3,653) - $ |
$28,174 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost |