IAC Assessment: BD0114
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0114
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 1998
Principal Product Turbine Pumps
NAICS n/a
SIC 3561 - Pumps And Pumping Equipment
Sales $1,000,000-$5,000,000
# of Employees 62
Plant Area (Sq.Ft.) 93,517
Annual Production 1,275 Pieces
Production Hrs. Annual 2,210
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $51,799 1,257,034 kWh $0.04
Electricity Demand $29,013 3,994 kW-months/year $7.26
Electricity Fees $3,200 - $ -
Natural Gas $39,363 7,685 MMBtu $5.12
TOTAL ENERGY COSTS $127,851
RECOMMENDED SAVINGS* $31,782 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,800
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ gal $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,281
Cost:
$15,250
$5,307 126,905 $3,545 488 - - - - $429 - $5,307
126,905
kWh
$3,545
488
kW-months/year
-
-
MMBtu
-
-
gal
$429
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$5,471
Cost:
$2,025
$3,502 83,822 $1,969 271 - - - - - - $3,502
83,822
kWh
$1,969
271
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
03: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE Savings:
$2,053
Cost:
$5,000
- - - - $2,053 416 - - - - -
-
kWh
-
-
kW-months/year
$2,053
416
MMBtu
-
-
gal
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,083
Cost:
$2,257
$649 15,533 $434 60 - - - - - - $649
15,533
kWh
$434
60
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$281
Cost:
$200
$168 4,103 $113 16 - - - - - - $168
4,103
kWh
$113
16
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
06: 3.5111 FILTER AND REUSE HYDRAULIC OIL Savings:
$4,256
Cost:
$1,125
- - - - - - - - $4,256 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$4,256
-
$
07: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$2,147
Cost:
$250
- - - - - - - - $2,147 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$2,147
-
$
08: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$1,921
Cost:
$1,300
- - - - - - $1,921 84 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,921
84
gal
-
-
$
09: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL Savings:
$5,289
Cost:
$4,395
- - - - - - - - $5,289 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$5,289
-
$
TOTAL RECOMMENDED Savings:
$31,782
Cost:
$31,802
$9,626 230,363 $6,061 835 $2,053 416 $1,921 84 $12,121 - $9,626
230,363
kWh
$6,061
835
kW-months/year
$2,053
416
MMBtu
$1,921
84
gal
$12,121
-
$
TOTAL IMPLEMENTED Savings:
$17,800
Cost:
$22,152
$5,956 142,438 $3,979 548 - - - - $7,865 - $5,956
142,438
kWh
$3,979
548
kW-months/year
-
-
MMBtu
-
-
gal
$7,865
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes