IAC Assessment: BD0120
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0120
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 1998
Principal Product cold drawn steel tubing
NAICS n/a
SIC 3317 - Steel Pipe And Tubes
Sales $10,000,000-$50,000,000
# of Employees 89
Plant Area (Sq.Ft.) 14,000,000
Annual Production 14,000 Thousand Feet
Production Hrs. Annual 7,488
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $64,337 2,207,503 kWh $0.03
Electricity Demand $59,989 4,822 kW-months/year $12.44
Electricity Fees $561 - $ -
Natural Gas $250,001 80,353 MMBtu $3.11
TOTAL ENERGY COSTS $397,918
RECOMMENDED SAVINGS* $31,571 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,275
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$13,459
Cost:
$600
$8,476 250,000 $4,983 401 - - - - - - - - $8,476
250,000
kWh
$4,983
401
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
02: 2.7496 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE Savings:
$4,250
Cost:
$4,000
- - - - $4,250 1,345 - - - - - - -
-
kWh
-
-
kW-months/year
$4,250
1,345
MMBtu
-
-
Tgal
-
-
$
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$3,816
Cost:
$11,230
$2,650 78,253 $1,166 94 - - - - - - - - $2,650
78,253
kWh
$1,166
94
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$2,527
Cost:
$400
$1,481 43,669 $909 73 - - - - - - $137 - $1,481
43,669
kWh
$909
73
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
$137
-
$
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,992
Cost:
$500
$1,254 36,928 $738 59 - - - - - - - - $1,254
36,928
kWh
$738
59
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$985
Cost:
$750
$503 14,947 $482 39 - - - - - - - - $503
14,947
kWh
$482
39
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
07: 3.4151 MINIMIZE WATER USAGE Savings:
$1,780
Cost:
$750
- - - - - - $1,780 131,040 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,780
131,040
Tgal
-
-
$
-
-
$
08: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS Savings:
$2,430
Cost:
$1,000
- - - - - - - - $2,430 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,430
-
$
-
-
$
09: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$332
Cost:
-
- - - - - - - - - - $332 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
$332
-
$
TOTAL RECOMMENDED Savings:
$31,571
Cost:
$19,230
$14,364 423,797 $8,278 666 $4,250 1,345 $1,780 131,040 $2,430 - $469 - $14,364
423,797
kWh
$8,278
666
kW-months/year
$4,250
1,345
MMBtu
$1,780
131,040
Tgal
$2,430
-
$
$469
-
$
TOTAL IMPLEMENTED Savings:
$17,275
Cost:
$11,830
$11,126 328,253 $6,149 495 - - - - - - - - $11,126
328,253
kWh
$6,149
495
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Administrative Changes