IAC Assessment: BD0177
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0177
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 2001
Principal Product Ferrous Products/Aluminum
NAICS n/a
SIC 3599 - Industrial Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 115
Plant Area (Sq.Ft.) 201,000
Annual Production 0 Units
Production Hrs. Annual 8,008
Location (State) IL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $212,359 6,193,142 kWh $0.03
Electricity Demand $155,286 16,872 kW-months/year $9.20
Electricity Fees $7,106 - $ -
Natural Gas $64,554 13,927 MMBtu $4.64
TOTAL ENERGY COSTS $447,922
RECOMMENDED SAVINGS* $75,579 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,288
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #1 Personnel Changes Administrative Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Fuel Oil #1 Personnel Changes Administrative Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,288
Cost:
$500
$2,346 68,288 $942 102 - - - - - - - - $2,346
68,288
kWh
$942
102
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,171
Cost:
$1,425
$2,036 59,496 $1,135 123 - - - - - - - - $2,036
59,496
kWh
$1,135
123
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
03: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$2,294
Cost:
$500
$1,636 47,773 $658 72 - - - - - - - - $1,636
47,773
kWh
$658
72
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,988
Cost:
-
$1,418 41,325 $570 62 - - - - - - - - $1,418
41,325
kWh
$570
62
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,694
Cost:
$3,090
$1,302 38,101 $392 43 - - - - - - - - $1,302
38,101
kWh
$392
43
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$726
Cost:
$500
$518 15,240 $208 23 - - - - - - - - $518
15,240
kWh
$208
23
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
07: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$31,899
Cost:
$40,000
- - - - $23,309 5,129 $8,590 - - - - - -
-
kWh
-
-
kW-months/year
$23,309
5,129
MMBtu
$8,590
-
$
-
-
$
-
-
$
08: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$27,022
Cost:
$30,000
- - - - - - - - $27,022 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$27,022
-
$
-
-
$
09: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$3,497
Cost:
$10,000
$(-4,353) (-126,905) $(-1,750) (-190) - - - - - - $9,600 - $(-4,353)
(-126,905)
kWh
$(-1,750)
(-190)
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
$9,600
-
$
TOTAL RECOMMENDED Savings:
$75,579
Cost:
$86,015
$4,903 143,318 $2,155 235 $23,309 5,129 $8,590 - $27,022 - $9,600 - $4,903
143,318
kWh
$2,155
235
kW-months/year
$23,309
5,129
MMBtu
$8,590
-
$
$27,022
-
$
$9,600
-
$
TOTAL IMPLEMENTED Savings:
$3,288
Cost:
$500
$2,346 68,288 $942 102 - - - - - - - - $2,346
68,288
kWh
$942
102
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Fuel Oil #1 Personnel Changes Administrative Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Fuel Oil #1 Personnel Changes Administrative Changes One-time Revenue or Avoided Cost