Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2004 |
Principal Product | Tractor cabs and Fuel |
NAICS | 332999 - All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 281 |
Plant Area (Sq.Ft.) | 155,000 |
Annual Production | 117,750 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $227,014 | 6,244,163 | kWh | $0.04 |
Electricity Demand | $96,061 | 15,801 | kW-months/year | $6.08 |
Electricity Fees | $1,545 | - | $ | - |
Natural Gas | $303,078 | 44,114 | MMBtu | $6.87 |
TOTAL ENERGY COSTS | $687,687 | |||
RECOMMENDED SAVINGS* | $134,848 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $100,379 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $34,022 Cost: $1,900 |
$27,681 | 760,539 | $6,341 | 1,042 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$27,681 760,539 kWh |
$6,341 1,042 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $24,721 Cost: $500 |
- | - | $24,721 | 3,992 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$24,721 3,992 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $18,512 Cost: $44,500 |
- | - | $18,512 | 1,738 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$18,512 1,738 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2533 REPLACE AIR CURTAIN DOORS WITH SOLID DOORS |
Savings: $15,124 Cost: $6,800 |
- | - | - | - | $15,124 | 2,202 | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$15,124 2,202 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $5,880 Cost: $20,000 |
- | - | - | - | $1,966 | 286 | - | - | - | - | $3,914 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,966 286 MMBtu |
- - Tgal |
- - lb |
$3,914 - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $3,573 Cost: $320 |
$2,908 | 79,878 | $665 | 109 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,908 79,878 kWh |
$665 109 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $3,573 Cost: $450 |
$2,908 | 79,887 | $665 | 109 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,908 79,887 kWh |
$665 109 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,621 Cost: - |
$2,133 | 58,597 | $488 | 80 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$2,133 58,597 kWh |
$488 80 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $636 Cost: $1,200 |
$276 | 7,545 | $324 | 53 | - | - | - | - | - | - | $6 | - | - | - | $30 | - | - | - |
$276 7,545 kWh |
$324 53 kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
$6 - $ |
- - $ |
$30 - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $278 Cost: $434 |
$69 | 1,884 | - | - | $209 | 30 | - | - | - | - | - | - | - | - | - | - | - | - |
$69 1,884 kWh |
- - kW-months/year |
$209 30 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $15,320 Cost: $180 |
- | - | - | - | - | - | - | - | $15,320 | 127,750 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$15,320 127,750 lb |
- - $ |
- - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $1,425 Cost: $500 |
- | - | - | - | - | - | $870 | 324,482 | - | - | - | - | - | - | - | - | $555 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$870 324,482 Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
$555 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $9,163 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $9,163 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
$9,163 - $ |
- - $ |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $134,848 Cost: $76,784 |
$35,975 | 988,330 | $51,716 | 7,124 | $17,299 | 2,518 | $870 | 324,482 | $15,320 | 127,750 | $3,920 | - | $9,163 | - | $30 | - | $555 | - | $35,975 988,330 kWh |
$51,716 7,124 kW-months/year |
$17,299 2,518 MMBtu |
$870 324,482 Tgal |
$15,320 127,750 lb |
$3,920 - $ |
$9,163 - $ |
$30 - $ |
$555 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $100,379 Cost: $10,650 |
$35,630 | 978,901 | $32,880 | 5,333 | $15,124 | 2,202 | $870 | 324,482 | $15,320 | 127,750 | - | - | - | - | - | - | $555 | - | $35,630 978,901 kWh |
$32,880 5,333 kW-months/year |
$15,124 2,202 MMBtu |
$870 324,482 Tgal |
$15,320 127,750 lb |
- - $ |
- - $ |
- - $ |
$555 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption |