IAC Assessment: BD0277
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BD0277
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Bradley University
Assessment Year 2005
Principal Product Replacement Form Coils for Rotating Electrical Apparatus
NAICS 335312 - Motor and Generator Manufacturing
SIC 3621 - Motors And Generators
Sales $1,000,000-$5,000,000
# of Employees 43
Plant Area (Sq.Ft.) 64,000
Annual Production 1,000 Pieces
Production Hrs. Annual 2,340
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $30,117 539,904 kWh $0.06
Electricity Demand $17,710 2,127 kW-months/year $8.33
Natural Gas $19,643 3,272 MMBtu $6.00
LPG $29,430 2,638 MMBtu $11.16
TOTAL ENERGY COSTS $97,833
RECOMMENDED SAVINGS* $27,039 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,996
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,390
Cost:
$1,400
$4,188 75,063 $3,202 385 - - - - - - - - $4,188
75,063
kWh
$3,202
385
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,675
Cost:
$2,008
$2,567 45,995 $1,963 236 - - $46 - $99 - - - $2,567
45,995
kWh
$1,963
236
kW-months/year
-
-
MMBtu
$46
-
$
$99
-
$
-
-
$
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$2,870
Cost:
$4,800
$500 8,938 $160 19 $2,210 370 - - - - - - $500
8,938
kWh
$160
19
kW-months/year
$2,210
370
MMBtu
-
-
$
-
-
$
-
-
$
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,514
Cost:
$1,200
- - - - $1,514 252 - - - - - - -
-
kWh
-
-
kW-months/year
$1,514
252
MMBtu
-
-
$
-
-
$
-
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,482
Cost:
-
$840 15,054 $642 77 - - - - - - - - $840
15,054
kWh
$642
77
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,301
Cost:
$800
$735 13,173 $566 68 - - - - - - - - $735
13,173
kWh
$566
68
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
07: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT Savings:
$736
Cost:
-
- - - - $736 123 - - - - - - -
-
kWh
-
-
kW-months/year
$736
123
MMBtu
-
-
$
-
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$426
Cost:
$297
$241 4,315 $50 6 - - $65 - $70 - - - $241
4,315
kWh
$50
6
kW-months/year
-
-
MMBtu
$65
-
$
$70
-
$
-
-
$
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$395
Cost:
$525
$202 3,638 $193 23 - - - - - - - - $202
3,638
kWh
$193
23
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
10: 4.447 AUTOMATE PAYROLL SYSTEM Savings:
$4,368
Cost:
$2,500
- - - - - - $4,368 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$4,368
-
$
-
-
$
-
-
$
11: 4.632 CHANGE OPERATING CONDITIONS Savings:
$1,882
Cost:
-
- - - - - - - - - - $1,882 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
$1,882
-
$
TOTAL RECOMMENDED Savings:
$27,039
Cost:
$13,530
$9,273 166,176 $6,776 814 $4,460 745 $4,479 - $169 - $1,882 - $9,273
166,176
kWh
$6,776
814
kW-months/year
$4,460
745
MMBtu
$4,479
-
$
$169
-
$
$1,882
-
$
TOTAL IMPLEMENTED Savings:
$17,996
Cost:
$9,022
$6,706 120,181 $4,813 578 $4,460 745 $65 - $70 - $1,882 - $6,706
120,181
kWh
$4,813
578
kW-months/year
$4,460
745
MMBtu
$65
-
$
$70
-
$
$1,882
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost One-time Revenue or Avoided Cost