Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2007 |
Principal Product | Injection Molded Plastics |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 17,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $172,485 | 5,914,990 | kWh | $0.03 |
Electricity Demand | $84,487 | 12,898 | kW-months/year | $6.55 |
Natural Gas | $8,186 | 2,108 | MMBtu | $3.88 |
TOTAL ENERGY COSTS | $265,158 | |||
RECOMMENDED SAVINGS* | $50,257 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $20,588 Cost: $1,951 |
$12,511 | 1,463 | $8,077 | 1,233 | - | - | - | - | - | - |
$12,511 1,463 kWh |
$8,077 1,233 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $608 Cost: $1,401 |
$98 | 12 | $506 | 78 | - | - | $4 | - | - | - |
$98 12 kWh |
$506 78 kW-months/year |
- - MMBtu |
$4 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $274 Cost: $476 |
$136 | 16 | $42 | 7 | - | - | $40 | - | $56 | - |
$136 16 kWh |
$42 7 kW-months/year |
- - MMBtu |
$40 - $ |
$56 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $272 Cost: $2 |
$190 | 22 | $82 | 13 | - | - | - | - | - | - |
$190 22 kWh |
$82 13 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $496 Cost: $351 |
$346 | 41 | $150 | 23 | - | - | - | - | - | - |
$346 41 kWh |
$150 23 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $23,837 Cost: $40,001 |
- | - | - | - | $23,837 | 2,272 | - | - | - | - |
- - kWh |
- - kW-months/year |
$23,837 2,272 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $4,182 Cost: $2 |
$2,924 | 342 | $1,258 | 192 | - | - | - | - | - | - |
$2,924 342 kWh |
$1,258 192 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $50,257 Cost: $44,184 |
$16,205 | 1,896 | $10,115 | 1,546 | $23,837 | 2,272 | $44 | - | $56 | - | $16,205 1,896 kWh |
$10,115 1,546 kW-months/year |
$23,837 2,272 MMBtu |
$44 - $ |
$56 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material |