Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2009 |
Principal Product | Die Cut Lidding |
NAICS | 322220 - Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2671 - Paper Coated & Laminated, Packaging |
Sales | $50,000,000-$100,000,000 |
# of Employees | 122 |
Plant Area (Sq.Ft.) | 86,000 |
Annual Production | 2,147,483,647 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $278,710 | 3,925,008 | kWh | $0.07 |
Electricity Demand | $44,591 | 20,955 | kW-months/year | $2.13 |
Electricity Fees | $14,663 | - | $ | - |
Natural Gas | $199,101 | 16,847 | MMBtu | $11.82 |
TOTAL ENERGY COSTS | $539,514 | |||
RECOMMENDED SAVINGS* | $458,177 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $359,522 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $4,893 Cost: $241 |
$3,871 | 51,868 | $208 | 98 | - | - | $513 | - | $301 | - |
$3,871 51,868 kWh |
$208 98 kW-months/year |
- - MMBtu |
$513 - $ |
$301 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $565 Cost: $491 |
$375 | 5,326 | $16 | 7 | - | - | $80 | - | $94 | - |
$375 5,326 kWh |
$16 7 kW-months/year |
- - MMBtu |
$80 - $ |
$94 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $10,495 Cost: $3,961 |
$8,359 | 118,565 | $1,108 | 520 | - | - | $514 | - | $514 | - |
$8,359 118,565 kWh |
$1,108 520 kW-months/year |
- - MMBtu |
$514 - $ |
$514 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,911 Cost: $2 |
$1,802 | 25,563 | $109 | 49 | - | - | - | - | - | - |
$1,802 25,563 kWh |
$109 49 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $24,734 Cost: $501 |
- | - | - | - | $24,734 | 2,093 | - | - | - | - |
- - kWh |
- - kW-months/year |
$24,734 2,093 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1224 REPLACE BOILER |
Savings: $9,256 Cost: $601 |
- | - | - | - | $9,256 | 783 | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,256 783 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $34,960 Cost: $24,000 |
- | - | - | - | $6,772 | 573 | $28,188 | - | - | - |
- - kWh |
- - kW-months/year |
$6,772 573 MMBtu |
$28,188 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $32,157 Cost: $5,301 |
- | - | - | - | $32,157 | 2,725 | - | - | - | - |
- - kWh |
- - kW-months/year |
$32,157 2,725 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $339,206 Cost: $5,001 |
- | - | - | - | - | - | $339,206 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$339,206 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $458,177 Cost: $40,099 |
$14,407 | 201,322 | $1,441 | 674 | $72,919 | 6,174 | $368,501 | - | $909 | - | $14,407 201,322 kWh |
$1,441 674 kW-months/year |
$72,919 6,174 MMBtu |
$368,501 - $ |
$909 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $359,522 Cost: $10,054 |
$8,734 | 123,891 | $1,124 | 527 | $9,256 | 783 | $339,800 | - | $608 | - | $8,734 123,891 kWh |
$1,124 527 kW-months/year |
$9,256 783 MMBtu |
$339,800 - $ |
$608 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Primary Raw Material |