Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Bradley University |
---|---|
Assessment Year | 2013 |
Principal Product | Non-ferrous castings |
NAICS | 331523 - Nonferrous Metal Die-Casting Foundries |
SIC | 3364 - Nonferrous Die-casting Exc. Aluminum |
Sales | $10,000,000-$50,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 126,175 |
Annual Production | 1 Units |
Production Hrs. Annual | 5,616 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $284,112 | 5,724,203 | kWh | $0.05 |
Electricity Demand | $18,557 | 17,181 | kW-months/year | $1.08 |
Electricity Fees | $12,676 | - | $ | - |
Natural Gas | $158,678 | 31,427 | MMBtu | $5.05 |
TOTAL ENERGY COSTS | $474,023 | |||
RECOMMENDED SAVINGS* | $84,973 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,382 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $22,668 Cost: $34,200 |
- | - | - | - | $22,668 | 4,490 |
- - kWh |
- - kW-months/year |
$22,668 4,490 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $28,900 Cost: $16,000 |
- | - | - | - | $28,900 | 5,730 |
- - kWh |
- - kW-months/year |
$28,900 5,730 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,154 Cost: $1,077 |
- | - | - | - | $1,154 | 229 |
- - kWh |
- - kW-months/year |
$1,154 229 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $25,547 Cost: $50,250 |
$24,539 | 492,684 | $1,008 | 934 | - | - |
$24,539 492,684 kWh |
$1,008 934 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,445 Cost: $4,125 |
$2,298 | 46,336 | $147 | 136 | - | - |
$2,298 46,336 kWh |
$147 136 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,044 Cost: $3,000 |
$1,936 | 39,003 | $108 | 100 | - | - |
$1,936 39,003 kWh |
$108 100 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $578 Cost: $20 |
$547 | 9,796 | $31 | 28 | - | - |
$547 9,796 kWh |
$31 28 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $1,637 Cost: $600 |
$1,540 | 31,021 | $97 | 90 | - | - |
$1,540 31,021 kWh |
$97 90 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $84,973 Cost: $109,272 |
$30,860 | 618,840 | $1,391 | 1,288 | $52,722 | 10,449 | $30,860 618,840 kWh |
$1,391 1,288 kW-months/year |
$52,722 10,449 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,382 Cost: $54,927 |
$28,015 | 562,708 | $1,213 | 1,123 | $1,154 | 229 | $28,015 562,708 kWh |
$1,213 1,123 kW-months/year |
$1,154 229 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |