Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Boise State University |
---|---|
Assessment Year | 2019 |
Principal Product | Lumber |
NAICS | 321113 - Sawmills |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $100,000,000-$500,000,000 |
# of Employees | 185 |
Plant Area (Sq.Ft.) | 5,690,341 |
Annual Production | 256,000 Thousand Feet |
Production Hrs. Annual | 4,807 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $905,874 | 27,380,507 | kWh | $0.03 |
Electricity Demand | $161,835 | 49,927 | kW-months/year | $3.24 |
Natural Gas | $237,930 | 59,286 | MMBtu | $4.01 |
TOTAL ENERGY COSTS | $1,305,638 | |||
RECOMMENDED SAVINGS* | $458,837 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,031 Cost: $14,455 |
$8,051 | 243,984 | $1,979 | 609 | - | - |
$8,051 243,984 kWh |
$1,979 609 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $13,702 Cost: $8,000 |
$4,777 | 144,759 | $8,925 | 2,746 | - | - |
$4,777 144,759 kWh |
$8,925 2,746 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,341 Cost: $1,630 |
$2,407 | 72,971 | $934 | 287 | - | - |
$2,407 72,971 kWh |
$934 287 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $882 Cost: $15 |
$882 | 26,710 | - | - | - | - |
$882 26,710 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $2,219 Cost: $5,725 |
$2,219 | 69,432 | - | - | - | - |
$2,219 69,432 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL |
Savings: $105,689 Cost: $93,600 |
- | - | - | - | $105,689 | 26,337 |
- - kWh |
- - kW-months/year |
$105,689 26,337 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3414 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT |
Savings: $322,973 Cost: $1,002,400 |
$322,973 | 9,825,508 | - | - | - | - |
$322,973 9,825,508 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $458,837 Cost: $1,125,825 |
$341,310 | 10,383,364 | $11,838 | 3,642 | $105,689 | 26,337 | $341,310 10,383,364 kWh |
$11,838 3,642 kW-months/year |
$105,689 26,337 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |