Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Clemson University |
---|---|
Assessment Year | 2019 |
Principal Product | Muffins, cookies, frozen dough |
NAICS | 311812 - Commercial Bakeries |
SIC | 2051 - Bread, Cake, And Related Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 425 |
Plant Area (Sq.Ft.) | 212,000 |
Annual Production | 240,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | SC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $935,272 | 19,358,612 | kWh | $0.05 |
Electricity Demand | $543,948 | 43,200 | kW-months/year | $12.59 |
Electricity Fees | $20,765 | - | $ | - |
Natural Gas | $88,836 | 20,111 | MMBtu | $4.42 |
TOTAL ENERGY COSTS | $1,588,821 | |||
RECOMMENDED SAVINGS* | $22,242 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $19,622 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,145 Cost: $2,800 |
$2,314 | 46,267 | $831 | 66 |
$2,314 46,267 kWh |
$831 66 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,477 Cost: $30,884 |
$9,147 | 182,933 | $7,330 | 582 |
$9,147 182,933 kWh |
$7,330 582 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,620 Cost: - |
$1,927 | 38,546 | $693 | 55 |
$1,927 38,546 kWh |
$693 55 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,242 Cost: $33,684 |
$13,388 | 267,746 | $8,854 | 703 | $13,388 267,746 kWh |
$8,854 703 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $19,622 Cost: $33,684 |
$11,461 | 229,200 | $8,161 | 648 | $11,461 229,200 kWh |
$8,161 648 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |