IAC Assessment: CO0022
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0022
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 1985
Principal Product PLEXIGLASS SKYLIGHTS
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $1,000,000-$5,000,000
# of Employees 70
Plant Area (Sq.Ft.) 0
Annual Production 1,100,000 Pieces
Production Hrs. Annual 2,470
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $48,048 454,865 kWh $0.11
Natural Gas $25,956 5,145 MMBtu $5.04
TOTAL ENERGY COSTS $74,004
RECOMMENDED SAVINGS* $13,408 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,354
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,005
Cost:
$812
$3,005 28,429 - - - - $3,005
28,429
kWh
-
-
MMBtu
-
-
$
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$235
Cost:
$300
- - $235 47 - - -
-
kWh
$235
47
MMBtu
-
-
$
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$3,655
Cost:
$5,000
$3,655 - - - - - $3,655
-
kWh
-
-
MMBtu
-
-
$
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,408
Cost:
$2,500
$1,766 16,706 $(-358) (-71) - - $1,766
16,706
kWh
$(-358)
(-71)
MMBtu
-
-
$
05: 2.1135 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY Savings:
$111
Cost:
$100
- - $111 22 - - -
-
kWh
$111
22
MMBtu
-
-
$
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$1,775
Cost:
$100
$1,775 16,706 - - - - $1,775
16,706
kWh
-
-
MMBtu
-
-
$
07: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$1,991
Cost:
$4,000
- - $1,991 395 - - -
-
kWh
$1,991
395
MMBtu
-
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$898
Cost:
$100
$898 8,499 - - - - $898
8,499
kWh
-
-
MMBtu
-
-
$
09: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$253
Cost:
$12
$31 293 $222 44 - - $31
293
kWh
$222
44
MMBtu
-
-
$
10: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT Savings:
$77
Cost:
-
- - $237 47 $(-160) - -
-
kWh
$237
47
MMBtu
$(-160)
-
$
TOTAL RECOMMENDED Savings:
$13,408
Cost:
$12,924
$11,130 70,633 $2,438 484 $(-160) - $11,130
70,633
kWh
$2,438
484
MMBtu
$(-160)
-
$
TOTAL IMPLEMENTED Savings:
$6,354
Cost:
$1,424
$5,709 53,927 $805 160 $(-160) - $5,709
53,927
kWh
$805
160
MMBtu
$(-160)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes