Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1985 |
Principal Product | STAINLESS STEEL FOOD EQUIPMENT |
NAICS | n/a |
SIC | 3556 - Food Products Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 4,000,000 Pounds |
Production Hrs. Annual | 4,420 |
Location (State) | WY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $116,220 | 2,961,899 | kWh | $0.04 |
Natural Gas | $75,402 | 21,006 | MMBtu | $3.59 |
TOTAL ENERGY COSTS | $191,622 | |||
RECOMMENDED SAVINGS* | $27,680 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $20,422 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $253 Cost: $250 |
$253 | 6,448 | - | - | - | - |
$253 6,448 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $666 Cost: $500 |
$666 | 16,999 | - | - | - | - |
$666 16,999 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,591 Cost: $200 |
- | - | $4,591 | 1,101 | - | - |
- - kWh |
$4,591 1,101 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $475 Cost: $534 |
- | - | $475 | 114 | - | - |
- - kWh |
$475 114 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,363 Cost: $200 |
$2,363 | - | - | - | - | - |
$2,363 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,589 Cost: $300 |
- | - | $1,589 | 381 | - | - |
- - kWh |
$1,589 381 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1222 INSTALL TURBULATORS |
Savings: $1,268 Cost: $500 |
- | - | $1,268 | 304 | - | - |
- - kWh |
$1,268 304 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,801 Cost: $1,500 |
- | - | $1,801 | 432 | - | - |
- - kWh |
$1,801 432 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $555 Cost: $700 |
- | - | $555 | 133 | - | - |
- - kWh |
$555 133 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $3,094 Cost: $5,000 |
- | - | $3,094 | 742 | - | - |
- - kWh |
$3,094 742 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $3,959 Cost: $9,000 |
- | - | $3,002 | 720 | $957 | - |
- - kWh |
$3,002 720 MMBtu |
$957 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $7,066 Cost: $1,000 |
$7,066 | 180,246 | - | - | - | - |
$7,066 180,246 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $27,680 Cost: $19,684 |
$10,348 | 203,693 | $16,375 | 3,927 | $957 | - | $10,348 203,693 kWh |
$16,375 3,927 MMBtu |
$957 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $20,422 Cost: $12,984 |
$7,985 | 203,693 | $11,480 | 2,753 | $957 | - | $7,985 203,693 kWh |
$11,480 2,753 MMBtu |
$957 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |