Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1987 |
Principal Product | METAL ELECTRICAL ENCLOSURES |
NAICS | n/a |
SIC | 3469 - Metal Stampings, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 115 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,000,000 Pounds |
Production Hrs. Annual | 2,210 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $81,489 | 1,317,409 | kWh | $0.06 |
Natural Gas | $55,134 | 13,688 | MMBtu | $4.03 |
TOTAL ENERGY COSTS | $136,623 | |||
RECOMMENDED SAVINGS* | $22,418 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,551 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $867 Cost: $1,200 |
- | - | $867 | 217 |
- - kWh |
$867 217 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $573 Cost: $540 |
$573 | 9,379 | - | - |
$573 9,379 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $683 Cost: $900 |
- | - | $683 | 169 |
- - kWh |
$683 169 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $2,672 Cost: $45 |
$605 | 9,672 | $2,067 | 513 |
$605 9,672 kWh |
$2,067 513 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $3,517 Cost: $250 |
$1,767 | - | $1,750 | - |
$1,767 - kWh |
$1,750 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,069 Cost: $500 |
$1,069 | - | - | - |
$1,069 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $12,647 Cost: $2,000 |
- | - | $12,647 | 3,138 |
- - kWh |
$12,647 3,138 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $390 Cost: $796 |
$390 | 6,448 | - | - |
$390 6,448 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,418 Cost: $6,231 |
$4,404 | 25,499 | $18,014 | 4,037 | $4,404 25,499 kWh |
$18,014 4,037 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,551 Cost: $5,031 |
$4,404 | 25,499 | $17,147 | 3,820 | $4,404 25,499 kWh |
$17,147 3,820 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |