Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1988 |
Principal Product | LAMB CARCASSES |
NAICS | n/a |
SIC | 2011 - Meat Packing Plants |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 750,000 Pieces |
Production Hrs. Annual | 8,736 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $103,574 | 2,143,611 | kWh | $0.05 |
Natural Gas | $98,569 | 27,064 | MMBtu | $3.64 |
TOTAL ENERGY COSTS | $202,143 | |||
RECOMMENDED SAVINGS* | $28,730 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,894 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $14,785 Cost: $2,000 |
- | - | $14,785 | - |
- - kWh |
$14,785 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,065 Cost: $7,500 |
- | - | $1,065 | 293 |
- - kWh |
$1,065 293 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $948 Cost: $1,000 |
- | - | $948 | 261 |
- - kWh |
$948 261 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $1,514 Cost: $500 |
$793 | 16,413 | $721 | 198 |
$793 16,413 kWh |
$721 198 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,211 Cost: $5,000 |
$1,127 | 23,447 | $1,084 | 298 |
$1,127 23,447 kWh |
$1,084 298 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,707 Cost: $3,035 |
$2,707 | 55,979 | - | - |
$2,707 55,979 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $911 Cost: $1,000 |
- | - | $911 | 250 |
- - kWh |
$911 250 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $3,677 Cost: $10,000 |
- | - | $3,677 | 1,010 |
- - kWh |
$3,677 1,010 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $659 Cost: $1,000 |
- | - | $659 | 181 |
- - kWh |
$659 181 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $253 Cost: $271 |
$253 | 5,275 | - | - |
$253 5,275 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,730 Cost: $31,306 |
$4,880 | 101,114 | $23,850 | 2,491 | $4,880 101,114 kWh |
$23,850 2,491 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,894 Cost: $15,306 |
$3,753 | 77,667 | $18,141 | 922 | $3,753 77,667 kWh |
$18,141 922 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |