Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1993 |
Principal Product | Refrigeration Equipment |
NAICS | n/a |
SIC | 3585 - Refrigeration And Heating Equipment |
Sales | $100,000,000-$500,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 275,000 |
Annual Production | 3,000 Pieces |
Production Hrs. Annual | 7,500 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $416,356 | 8,711,899 | kWh | $0.05 |
Natural Gas | $34,333 | 9,671 | MMBtu | $3.55 |
TOTAL ENERGY COSTS | $450,689 | |||
RECOMMENDED SAVINGS* | $47,530 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $36,630 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Primary Raw Material | Electricity Usage | Natural Gas | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7314 REDUCE VENTILATION AIR |
Savings: $6,130 Cost: $1,560 |
- | - | $6,130 | 1,500 | - | - |
- - kWh |
$6,130 1,500 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,760 Cost: $710 |
$7,760 | 162,368 | - | - | - | - |
$7,760 162,368 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $1,990 Cost: $100 |
$1,990 | 77,081 | - | - | - | - |
$1,990 77,081 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $14,570 Cost: $2,700 |
- | - | $14,570 | 1,690 | - | - |
- - kWh |
$14,570 1,690 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $530 Cost: $250 |
$530 | 11,137 | - | - | - | - |
$530 11,137 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $7,120 Cost: $8,160 |
- | - | - | - | $7,120 | - |
- - kWh |
- - MMBtu |
$7,120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $520 Cost: $750 |
$520 | 10,844 | - | - | - | - |
$520 10,844 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,350 Cost: $8,080 |
$4,350 | 90,856 | - | - | - | - |
$4,350 90,856 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $3,040 Cost: $6,200 |
$4,450 | 93,200 | $(-1,410) | (-398) | - | - |
$4,450 93,200 kWh |
$(-1,410) (-398) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,520 Cost: $4,500 |
$1,520 | 31,946 | - | - | - | - |
$1,520 31,946 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $47,530 Cost: $33,010 |
$21,120 | 477,432 | $19,290 | 2,792 | $7,120 | - | $21,120 477,432 kWh |
$19,290 2,792 MMBtu |
$7,120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $36,630 Cost: $14,130 |
$8,810 | 184,349 | $20,700 | 3,190 | $7,120 | - | $8,810 184,349 kWh |
$20,700 3,190 MMBtu |
$7,120 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Primary Raw Material | Electricity Usage | Natural Gas | Primary Raw Material |