IAC Assessment: CO0312
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0312
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 1994
Principal Product snowblowing vehicles
NAICS n/a
SIC 3711 - Motor Vehicles And Car Bodies
Sales $10,000,000-$50,000,000
# of Employees 170
Plant Area (Sq.Ft.) 65,000
Annual Production 30 Pieces
Production Hrs. Annual 2,210
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $71,900 1,096,424 kWh $0.07
Natural Gas $30,870 7,368 MMBtu $4.19
TOTAL ENERGY COSTS $102,770
RECOMMENDED SAVINGS* $9,000 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,790
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,660
Cost:
$3,200
$3,660 55,686 - - - - $3,660
55,686
kWh
-
-
MMBtu
-
-
$
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,960
Cost:
$1,050
$820 29,894 $1,140 271 - - $820
29,894
kWh
$1,140
271
MMBtu
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,410
Cost:
$210
$1,410 21,688 - - - - $1,410
21,688
kWh
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$790
Cost:
$(-290)
$790 12,016 - - - - $790
12,016
kWh
-
-
MMBtu
-
-
$
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$500
Cost:
$150
$500 7,620 - - - - $500
7,620
kWh
-
-
MMBtu
-
-
$
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$380
Cost:
$320
- - $380 91 - - -
-
kWh
$380
91
MMBtu
-
-
$
07: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$300
Cost:
$100
- - - - $300 - -
-
kWh
-
-
MMBtu
$300
-
$
TOTAL RECOMMENDED Savings:
$9,000
Cost:
$4,740
$7,180 126,904 $1,520 362 $300 - $7,180
126,904
kWh
$1,520
362
MMBtu
$300
-
$
TOTAL IMPLEMENTED Savings:
$6,790
Cost:
$4,280
$5,270 97,596 $1,520 362 - - $5,270
97,596
kWh
$1,520
362
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes