Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1995 |
Principal Product | Injection molded plastic parts |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 480,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $124,588 | 2,126,612 | kWh | $0.06 |
Natural Gas | $3,949 | 972 | MMBtu | $4.06 |
TOTAL ENERGY COSTS | $135,807 | |||
RECOMMENDED SAVINGS* | $8,010 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,640 |
#|Description |
Savings Cost |
Status | Electricity Usage | Other Liquid (haz) | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Other Liquid (haz) | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES |
Savings: $2,440 Cost: $80 |
- | - | - | - | - | - | $2,440 | - |
- - kWh |
- - gal |
- - lb |
$2,440 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,170 Cost: $5,580 |
$1,170 | 34,291 | - | - | - | - | - | - |
$1,170 34,291 kWh |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,740 Cost: $4,520 |
$1,740 | 34,877 | - | - | - | - | - | - |
$1,740 34,877 kWh |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $1,160 Cost: - |
- | - | - | - | $1,160 | 51,000 | - | - |
- - kWh |
- - gal |
$1,160 51,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $490 Cost: $2,080 |
$490 | 10,258 | - | - | - | - | - | - |
$490 10,258 kWh |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $400 Cost: $840 |
$400 | 9,379 | - | - | - | - | - | - |
$400 9,379 kWh |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES |
Savings: $370 Cost: $530 |
- | - | $370 | 170 | - | - | - | - |
- - kWh |
$370 170 gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $240 Cost: $80 |
- | - | - | - | - | 400 | $240 | - |
- - kWh |
- - gal |
- 400 lb |
$240 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,010 Cost: $13,710 |
$3,800 | 88,805 | $370 | 170 | $1,160 | 51,400 | $2,680 | - | $3,800 88,805 kWh |
$370 170 gal |
$1,160 51,400 lb |
$2,680 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,640 Cost: $13,180 |
$3,800 | 88,805 | - | - | $1,160 | 51,400 | $2,680 | - | $3,800 88,805 kWh |
- - gal |
$1,160 51,400 lb |
$2,680 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Other Liquid (haz) | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Other Liquid (haz) | Solid Waste (non-haz) | Ancillary Material Cost |