Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1995 |
Principal Product | Printed circuit boards |
NAICS | n/a |
SIC | 3672 - Printed Circuit Boards |
Sales | $5,000,000-$10,000,000 |
# of Employees | 72 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 979,400 Pieces |
Production Hrs. Annual | 6,864 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $113,946 | 1,706,331 | kWh | $0.07 |
Natural Gas | $5,723 | 1,307 | MMBtu | $4.38 |
TOTAL ENERGY COSTS | $198,429 | |||
RECOMMENDED SAVINGS* | $161,100 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,450 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Ancillary Material Cost | Electricity Usage | Natural Gas | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.5242 RECOVER METALS FROM SPENT SOLUTIONS AND RECYCLE |
Savings: $96,090 Cost: $153,400 |
- | - | - | - | $8,640 | 616,800 | $13,230 | 19,400 | - | - | $74,220 | - |
- - kWh |
- - MMBtu |
$8,640 616,800 Tgal |
$13,230 19,400 gal |
- - lb |
$74,220 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.3127 USE ADSORPTION, ION EXCHANGE TO REMOVE CONTAMINANTS |
Savings: $56,560 Cost: $174,500 |
- | - | - | - | $51,500 | 4,494,000 | - | - | $2,030 | 20,340 | $3,030 | - |
- - kWh |
- - MMBtu |
$51,500 4,494,000 Tgal |
- - gal |
$2,030 20,340 lb |
$3,030 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,910 Cost: $13,270 |
$4,910 | 89,977 | - | - | - | - | - | - | - | - | - | - |
$4,910 89,977 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,190 Cost: $1,240 |
$1,190 | 24,326 | - | - | - | - | - | - | - | - | - | - |
$1,190 24,326 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,000 Cost: $720 |
$1,000 | 19,930 | - | - | - | - | - | - | - | - | - | - |
$1,000 19,930 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $820 Cost: $600 |
- | - | $820 | 187 | - | - | - | - | - | - | - | - |
- - kWh |
$820 187 MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $530 Cost: - |
$530 | 11,137 | - | - | - | - | - | - | - | - | - | - |
$530 11,137 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $161,100 Cost: $343,730 |
$7,630 | 145,370 | $820 | 187 | $60,140 | 5,110,800 | $13,230 | 19,400 | $2,030 | 20,340 | $77,250 | - | $7,630 145,370 kWh |
$820 187 MMBtu |
$60,140 5,110,800 Tgal |
$13,230 19,400 gal |
$2,030 20,340 lb |
$77,250 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,450 Cost: $15,110 |
$6,630 | 125,440 | $820 | 187 | - | - | - | - | - | - | - | - | $6,630 125,440 kWh |
$820 187 MMBtu |
- - Tgal |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Ancillary Material Cost | Electricity Usage | Natural Gas | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Ancillary Material Cost |