Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1999 |
Principal Product | particleboard |
NAICS | n/a |
SIC | 2493 - Reconstituted Wood Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 140,000 |
Annual Production | 48,000,000 Thousand Feet |
Production Hrs. Annual | 8,712 |
Location (State) | NM |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $721,833 | 16,961,020 | kWh | $0.04 |
Electricity Demand | $311,769 | 31,224 | kW-months/year | $9.98 |
Electricity Fees | $74,159 | - | $ | - |
Natural Gas | $198,909 | 58,141 | MMBtu | $3.42 |
TOTAL ENERGY COSTS | $1,387,635 | |||
RECOMMENDED SAVINGS* | $130,400 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $41,240 Cost: $10,000 |
- | - | $41,240 | 3,579 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$41,240 3,579 kW-months/year |
- - Tgal |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,020 Cost: $220 |
$4,690 | 118,992 | $1,890 | 164 | - | - | - | - | - | - | $(-1,560) | - | - | - | - | - | - | - |
$4,690 118,992 kWh |
$1,890 164 kW-months/year |
- - Tgal |
- - gal |
- - lb |
$(-1,560) - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $2,640 Cost: - |
$1,400 | 27,843 | $1,240 | 107 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$1,400 27,843 kWh |
$1,240 107 kW-months/year |
- - Tgal |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $430 Cost: $440 |
$310 | 7,913 | $120 | 11 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$310 7,913 kWh |
$120 11 kW-months/year |
- - Tgal |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES |
Savings: $39,330 Cost: - |
- | - | - | - | $(-70) | (-26,020) | $38,440 | 6,506 | - | - | - | - | - | - | $960 | - | - | - |
- - kWh |
- - kW-months/year |
$(-70) (-26,020) Tgal |
$38,440 6,506 gal |
- - lb |
- - $ |
- - $ |
$960 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5314 USE IN-PROCESS RECYCLING WHENEVER POSSIBLE |
Savings: $2,180 Cost: $3,500 |
- | - | - | - | - | - | - | - | $280 | 75,800 | - | - | $1,900 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - gal |
$280 75,800 lb |
- - $ |
$1,900 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.624 HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME |
Savings: $39,560 Cost: $1,000 |
- | - | - | - | - | - | - | - | - | - | $(-40,000) | - | - | - | - | - | $79,560 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - gal |
- - lb |
$(-40,000) - $ |
- - $ |
- - $ |
$79,560 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $130,400 Cost: $15,160 |
$6,400 | 154,748 | $44,490 | 3,861 | $(-70) | (-26,020) | $38,440 | 6,506 | $280 | 75,800 | $(-41,560) | - | $1,900 | - | $960 | - | $79,560 | - | $6,400 154,748 kWh |
$44,490 3,861 kW-months/year |
$(-70) (-26,020) Tgal |
$38,440 6,506 gal |
$280 75,800 lb |
$(-41,560) - $ |
$1,900 - $ |
$960 - $ |
$79,560 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (haz) | Solid Waste (haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Primary Product |